Sweet Berry Farms Ltd.
Follow- Proceeding
- CCAAs. 11 of the CCAA
- File
- 2026 01G 0459
Sweet Berry Farms Ltd. obtained an initial order under s. 11 of the CCAA, heard February 17, 2026, in the Supreme Court of Newfoundland and Labrador (court file 2026 01G 0459), with a monitor appointed over the proceeding. A sale process was approved February 27, 2026. An internal creditor listing as at February 17, 2026 shows secured claims including Bank of Montreal at $3,340,512, Kubota Canada Ltd. at $678,884, and Agri Commodity Management Association at $463,191, and unsecured claims including M&M Farming Company Ltd. at $345,000, Shea's Building Supplies Limited at $196,283, and Classic Builders at $143,957.
The officer filed report no. Second Report. The Company wound down operations by liquidating its live hog inventory and frozen beef/pork through wholesale sales, ceased CCAA proceedings after no SISP bids were received, and BMO subsequently appointed MNP Ltd. as private receiver.
A sale process for Sweet Berry Farms Ltd. was approved February 27, 2026.
Source: Draft SISP Approval Order
Sweet Berry Farms Ltd. obtained an initial order under s. 11 of the CCAA, heard February 17, 2026.
Source: Draft Initial Order
Debtor
Sweet Berry Farms Ltd.
Monitor
Doane Grant Thornton
| # | Priority class | Creditor | Amount | Source |
|---|---|---|---|---|
| 4 | Secured | Bank of Montreal · in 279 casesInternal Creditor Listing as at February 17, 2026 — debtor: Sweet Berry Farms Ltd. · as of 17 Feb 2026 | $3.34M | Creditor Listing as of February 17, 2026 |
| 4 | Secured | Kubota Canada Ltd. · in 16 casesInternal Creditor Listing as at February 17, 2026 — debtor: Sweet Berry Farms Ltd. · as of 17 Feb 2026 | $679K | Creditor Listing as of February 17, 2026 |
| 4 | Secured | Agri Commodity Management AssociationInternal Creditor Listing as at February 17, 2026 — debtor: Sweet Berry Farms Ltd. · as of 17 Feb 2026 | $463K | Creditor Listing as of February 17, 2026 |
| 4 | Secured | KM Capital CorpInternal Creditor Listing as at February 17, 2026; amount listed as $1.00, possibly nominal/placeholder — debtor: Sweet Berry Farms Ltd. · as of 17 Feb 2026 | $1 | Creditor Listing as of February 17, 2026 |
| 8 | Unsecured | M&M Farming Company Ltd.debtor: Sweet Berry Farms Ltd. · as of 17 Feb 2026 | $345K | Creditor Listing as of February 17, 2026 |
| 8 | Unsecured | Shea's Building Supplies Limiteddebtor: Sweet Berry Farms Ltd. · as of 17 Feb 2026 | $196K | Creditor Listing as of February 17, 2026 |
| 8 | Unsecured | Classic Buildersdebtor: Sweet Berry Farms Ltd. · as of 17 Feb 2026 | $144K | Creditor Listing as of February 17, 2026 |
| 8 | Unsecured | Lawn & Farmdebtor: Sweet Berry Farms Ltd. · as of 17 Feb 2026 | $95.4K | Creditor Listing as of February 17, 2026 |
| 8 | Unsecured | BCJ Chartered Professional Accountantsdebtor: Sweet Berry Farms Ltd. · as of 17 Feb 2026 | $39.7K | Creditor Listing as of February 17, 2026 |
| 8 | Unsecured | Trouw Nutrition Canada Ltd.debtor: Sweet Berry Farms Ltd. · as of 17 Feb 2026 | $31.1K | Creditor Listing as of February 17, 2026 |
| 8 | Unsecured | Harvey Gale and Sonsdebtor: Sweet Berry Farms Ltd. · as of 17 Feb 2026 | $12K | Creditor Listing as of February 17, 2026 |
| 8 | Unsecured | Newfoundland Power · in 14 casesamount listed as $1.00, possibly nominal/placeholder — debtor: Sweet Berry Farms Ltd. · as of 17 Feb 2026 | $1 | Creditor Listing as of February 17, 2026 |
| 8 | Unsecured | Canada Revenue Agency · in 926 casesamount listed as $1.00, possibly nominal/placeholder — debtor: Sweet Berry Farms Ltd. · as of 17 Feb 2026 | $1 | Creditor Listing as of February 17, 2026 |
| 8 | Unsecured | Town of Stephenville Crossing · in 2 casesamount listed as $1.00, possibly nominal/placeholder — debtor: Sweet Berry Farms Ltd. · as of 17 Feb 2026 | $1 | Creditor Listing as of February 17, 2026 |
| 8 | Unsecured | WorkplaceNL · in 4 casesamount listed as $1.00, possibly nominal/placeholder — debtor: Sweet Berry Farms Ltd. · as of 17 Feb 2026 | $1 | Creditor Listing as of February 17, 2026 |
No acceptable bid — No bids were received in the SISP by the bid deadline, and the SISP has concluded without a transaction.Second Report of the Monitor dated May 29, 2026 · 29 May 2026
2 engagements · 2 firms — latest: (firm not named), —, $6,580.00 in feesSecond Report of the Monitor · 29 May 2026
| Firm | Period | Hours | Fees | Rates | Source |
|---|---|---|---|---|---|
| (firm not named)capacity not statedfirm not named in the heading | — | — | $6,580.00ex. tax | $470stated average | Second Report of the Monitor · 29 May 2026 |
| Grant Thornton LimitedMonitor | — | — | $94,092.50ex. tax | $403.83stated average | Second Report of the Monitor · 29 May 2026 |
Professional fees to date
$134K
As at 29 May 2026Second Report of the Monitor dated May 29, 2026
| Date | Document | File |
|---|---|---|
| Memorandum of Fact and Law dated July 14, 2026 | ||
| Interlocutory Application dated June 2, 2026 | ||
Second Report of the Monitor dated May 29, 2026
| ||
Report of Material Adverse Change dated April 24, 2026
| ||
| Solicitation Letter | ||
| Blackline Amended and Restated Initial Order | ||
| Draft Amended and Restated Initial Order | ||
Draft SISP Approval Order
| ||
| Affidavit of Thomas Hickey dated February 26, 2026 | ||
| Letter to the Court dated February 26, 2026 | ||
| Memorandum of Fact and Law dated February 26, 2026 | ||
| Notice of Motion dated February 26, 2026 | ||
| First Report of the Monitor dated February 25, 2026 | ||
| Notice to Creditors dated February 20, 2026 | ||
| BlackLine Initial Order | ||
| BlackLine Sealing Order | ||
| Blackline Charging Order | ||
| Confidentiality and Non-Disclosure Agreement | ||
Creditor Listing as of February 17, 2026
| ||
| Draft Amended Charging Order | ||
| Draft Charging Order | ||
Draft Initial Order
| ||
| Draft Sealing Order | ||
| SISP Procedures | ||
Pre-Filing Report of the Monitor dated February 16, 2026
| ||
| Applicant's Memorandum of Fact and Law dated February 13, 2026 | ||
| Consent to Act dated February 13, 2026 | ||
| Initial Affidavit of Thomas Hickey dated February 13, 2026 | ||
| Letter to Court dated February 13, 2026 | ||
| Notice of Application dated February 13, 2026 | ||
| Court Draft Charging Order | ||
| Court Draft Initial Order | ||
| Court Draft Sealing Order | ||
| Initial Order Redline | ||
Filing titles, dates, and extracted key facts are public.
CiteProceedings., “Sweet Berry Farms Ltd.” (CCAA), Supreme Court of Newfoundland and Labrador. Retrieved 20 September 2026, https://proceedings.ca/case/sweet-berry-farms-ltd