Receivership (court-appointed)section 243(1) of the Bankruptcy and Insolvency Act; and section 101 of the Courts of Justice Act
File
CV-24-00096502-0000
Filings held30
Last activity26 Oct 2026
On the record815 days
Secured debtSubscribers
OverviewSummary updated

Yeo Towns (2460467 Ontario Inc.) has been under the court-appointed receivership of KSV Restructuring Inc. since August 12, 2024, when the Ontario Superior Court of Justice appointed KSV as receiver and manager on the application of DUCA Financial Services Credit Union Ltd. under section 243 of the BIA and provincial Judicature Act authority, in court file CV-24-00096502-0000. DUCA holds a first-ranking mortgage on the real property and a general security agreement dated December 6, 2022, and was owed approximately $7,500,000 as at June 12, 2024, with interest and costs continuing to accrue, plus approximately $200,000 under a letter of credit facility. Westmount Guarantee Services Inc., ranking behind DUCA on a charge registered for $7,000,000 securing purchaser deposit insurance, is owed approximately $3,800,000 in released deposits. Eight suppliers have registered nine construction liens against the property, aggregating approximately $2 million. The proceeding remains active.

Ask in plain language. The answer comes only from this case’s filings, each one cited.
Enter to send · Shift+Enter for a new line
Open this case in Proceedings AI⁠Save your chats, keep long conversations going, and ask across every case.
Case updates30 dated entries
#Report

Reported the project behind schedule and over budget under construction manager Fusioncorp, with 35 purchaser terminations raising deposit and rescission issues, and appended fee affidavits covering August 12, 2024 to May 31, 2026.

Source: Third Report of the Receiver dated June 30, 2026

#Filing

DUCA Financial Services Credit Union Ltd. applied under section 243(1) of the Bankruptcy and Insolvency Act and section 101 of the Courts of Justice Act for the appointment of a receiver over 2460467 Ontario Inc.

Source: Notice of Application date July 18, 2024

Case update

Yeo Towns: no consent from HCRA, and a motion to replace Fusioncorp

The receiver says HCRA told it on September 21 that it would not consent to Fusioncorp staying on as construction manager. The court approved the unit sale process the next day; on October 19 the receiver sought approval to move Fusioncorp's contract to 59 Project Management at $10,500 a month, and moved its occupancy targets to December.

Case update

Yeo Towns: every trade paid through a lawyer's trust account

Two years and $13.5 million into completing a part-built 62-unit Belleville townhouse project, the receiver says it learned that the construction manager it had funded in full had been using the money for other purposes — and asks the court to keep the builder on site, pay every trade through a lawyer's trust account, and list the 37 units whose buyers rescinded.

Parties

Debtor

Yeo Towns (2460467 Ontario Inc.)

Receiver

KSV

Bench and counselPer the orders and service lists on the record

Bench

JudgeCourtOn this docketCases on record
Justice KershmanOntario Superior Court of Justice6 orders, Aug 2024 – Oct 202619 cases on record

Counsel of record

PartyCounselFirst seenSource
ReceiverKSVDickinson Wright LLP11 Dec 2024Order · 11 Dec 2024
ApplicantBorden Ladner Gervais LLP12 Aug 2024Order · 12 Aug 2024
DebtorYeo Towns (2460467 Ontario Inc.)Friedmans Law Firm6 Aug 2024Application · 6 Aug 2024
CreditorAviva Insurance Company of CanadaFasken Martineau DuMoulin LLP12 Aug 2024Service list · 12 Aug 2024
CreditorDUCA Financial Services Credit Union LtdBorden Ladner Gervais LLP12 Aug 2024Service list · 12 Aug 2024
CreditorKSV Restructuring IncDickinson Wright LLP12 Aug 2024Service list · 12 Aug 2024
Capital structureAs asserted in the filings
stated amounts, drawn to scale · for subscribers
#Priority classCreditorAmountSource
4SecuredDUCA Financial Services Credit Union Ltd. · in 19 casesFirst-ranking mortgage on the Real Property; general security agreement dated December 6, 2022 — Approximate balance per Duca's receivership application materials as of June 12, 2024 (prose approximation); interest and costs continuing to accrue. Also owed approximately $200,000 under a letter of credit facility as of the Filing Date (August 12, 2024) - separate entry below. As of the date of the Fourth Report (September 18, 2026), Duca's funding under the Receiver's Borrowing Charge totalled $13.5 million of the $16.15 million authorized under that charge (post-filing DIP financing, not pre-f · as of 12 Jun 2024$7.5MMotion Record of the Receiver dated September 18, 2026
4Secured
4Secured
4Secured
5PMSI / lessors
8Unsecured

5 more claims in 3 classes The stack holds Secured, PMSI / lessors and Unsecured claims.

Every creditor and every amount, drawn to scale.

Start 5-day trial

Card required. Nothing charged for 5 days. Cancel anytime.

Already a subscriber? Sign in.

See all plans⁠

This proceeding was commenced by a secured creditor. The record does not include the debtor’s own statement of assets and liabilities — that ceiling is the record’s, not this page’s.

Fees and ratesAs stated in the filings

2 engagements · 2 firms — latest: Dickinson Wright LLP, 26 Sep 2024 – 25 Jun 2026Third Report of the Receiver · 30 Jun 2026

FirmPeriodHoursFeesRatesSource
AlixPartners Restructuring, Inc.Receiver—Approved——Third Report of the Receiver · 30 Jun 2026
Dickinson Wright LLPCounsel26 Sep 2024 – 25 Jun 2026——Third Report of the Receiver · 30 Jun 2026

2 blurred figures above

What each firm billed — each as the filing states it, with its source.

Start 5-day trial

Card required. Nothing charged for 5 days. Cancel anytime.

Already a subscriber? Sign in.

See all plans⁠
Estate financialsReported figures — never derived

Cash on hand

$0

As at 30 Jun 2026Third Report of the Receiver dated June 30, 2026

Professional fees

As at

1 more reported figure

Each one as the filing states it, with its source.

Start 5-day trial

Card required. Nothing charged for 5 days. Cancel anytime.

Already a subscriber? Sign in.

See all plans⁠
Documents
30 filings
DateDocumentFile
Amended Endorsement of Justice Kershman dated October 26, 2026
  • Presiding officer Justice Kershman
PDF · Subscribers
Motion Record of the Receiver dated October 19, 2026
  • Financial position · Secured creditors · Unsecured creditors Subscribers
PDF · Subscribers
Supplement to the Fourth Report dated October 19, 2026
  • Operational summary The Receiver is overseeing completion of the construction project and, after HCRA objected to Fusioncorp continuing as construction manager, seeks approval of an Assignment and Amendment Agreement assigning the construction contract to 59 PM. Delays from the fund diversion issue have pushed target occupancy dates for the unit blocks into December 2026.
  • Cash on hand · Disbursements · Financial position Subscribers
  • + 6 more extracted facts
PDF · Subscribers
Endorsement of J. Kershman dated September 22, 2026PDF · Subscribers
Order dated September 22, 2026
  • Presiding officer Justice Kershman
PDF · Subscribers
Factum of the Receiver dated September 18, 2026
  • Counsel Dickinson Wright LLP
PDF · Subscribers
Fourth Report of the Receiver dated September 18, 2026
  • Financial position · Secured creditors · Unsecured creditors Subscribers
PDF · Subscribers
Motion Record of the Receiver dated September 18, 2026
  • Financial position · Secured creditors · Unsecured creditors Subscribers
PDF · Subscribers
Third Report of the Receiver dated July 16, 2026
PDF · Subscribers
Court Order dated July 8, 2026PDF · Subscribers
Motion Record of the Receiver dated June 30, 2026
PDF · Subscribers
Third Report of the Receiver dated June 30, 2026
  • Cash on hand · Disbursements · Fee schedule · Financial position Subscribers
  • + 5 more extracted facts
PDF · Subscribers
Court Order dated May 14, 2025
  • Counsel Dickinson Wright LLP
PDF · Subscribers
Endorsement of Justice Kershman dated May 14, 2025
  • Presiding officer Justice Kershman
PDF · Subscribers
Notice #2 to Unit Purchasers dated May 14, 2025PDF · Subscribers
Endorsement of Justice Kershman dated May 5, 2025
  • Counsel Dickinson Wright LLP
  • Presiding officer Justice Kershman
PDF · Subscribers
Factum of the Receiver dated May 2, 2025
  • Counsel Dickinson Wright LLP
PDF · Subscribers
Supplement to Second Report of the Receiver dated May 2, 2025
PDF · Subscribers
Motion Record of the Receiver dated April 30, 2025PDF · Subscribers
Second Report of the Receiver dated April 30, 2025
  • Operational summary Construction on the Project has been halted since before the receivership began (aside from winterization work), and the Receiver is now recommending Court approval of a Completion Agreement with Fusioncorp to recommence and complete the stalled 62-unit townhouse development.
  • Cash on hand · Disbursements · Financial position Subscribers
  • + 4 more extracted facts
PDF · Subscribers
Court Order dated December 11, 2024
  • Counsel Dickinson Wright LLP
  • Presiding officer Justice Kershman
PDF · Subscribers
First Report of the Receiver dated December 5, 2024
  • Financial position · Secured creditors · Unsecured creditors Subscribers
PDF · Subscribers
Motion Record of the Receiver dated December 5, 2024PDF · Subscribers
Notice to Unit Purchasers dated August 20, 2024
PDF · Subscribers
Receivership Appointment Order dated August 12, 2024
  • Applicant DUCA Financial Services Credit Union Ltd.
  • Appointee KSV Restructuring Inc.
  • Appointee role receiver and manager
  • Commencement date 12 August 2024
  • + 5 more extracted facts
PDF · Subscribers
Service List as at August 12, 2024
  • Counsel Fasken Martineau Dumoulin LLP
PDF · Subscribers
Reply Affidavit of Ivan Bogdanovich dated August 6, 2024PDF · Subscribers
Supplementary Responding Application Record dated August 6, 2024 (Redacted)
  • Counsel Friedmans LLP
PDF · Subscribers
Responding Application of Respondent dated July 31, 2024PDF · Subscribers
Notice of Application date July 18, 2024
  • Applicant DUCA FINANCIAL SERVICES CREDIT UNION LTD.
  • Appointee KSV Restructuring Inc.
  • Appointee role Receiver
  • Commencement date 18 July 2024
  • + 3 more extracted facts
PDF · Subscribers

Filing titles and dates are public, and so is each filing's own page. The figures read from them are for subscribers.

CiteProceedings., “Yeo Towns (2460467 Ontario Inc.)” (Receivership (court-appointed)), Ontario Superior Court of Justice. Retrieved 4 November 2026, https://proceedings.ca/case/yeo-towns-2460467-ontario-inc