Ontario · Receivership (court-appointed)
Supplement to the Fourth Report dated October 19, 2026
Court officer report · 19 October 2026
AI summary
A plain-English summary drawn only from this filing: what it is, why it matters, and the parties, amounts and dates it turns on.
What we verified from this filing3 verified
- operational summaryThe Receiver is overseeing completion of the construction project and, after HCRA objected to Fusioncorp continuing as construction manager, seeks approval of an Assignment and Amendment Agreement assigning the construction contract to 59 PM. Delays from the fund diversion issue have pushed target occupancy dates for the unit blocks into December 2026.
- report date19 October 2026
- report noSupplement to Fourth Report