Able Infrastructure Inc. and other affiliates including Precision Concrete Services Limited and related holding and operating companies
- Proceeding
- CCAACompanies' Creditors Arrangement Act, R.S.C. 1985, c. C-36
- File
- Hfx No. 548787
- Industry
- Construction
Able Infrastructure Inc., Bespoke Canadian Investments Inc. and Precision Concrete Services Limited have been under the Companies' Creditors Arrangement Act in the Supreme Court of Nova Scotia since November 25, 2025 (Hfx No. 548787), and the proceeding remains active. Able Infrastructure continues operating to complete its remaining contract, the Liam George project, while winding down and monitoring liquidity; Precision Concrete's operations have ceased following the transfer of its contracts to Highrise. Cash on hand was approximately $255,566 as at June 26, 2026. An internal creditor listing as at November 25, 2025 shows the Canada Revenue Agency owed $8,525,023 by Able Infrastructure Inc. and $2,807,887 by Precision Concrete Services Limited and Bespoke Canadian Investments Inc., for source deductions and GST/HST. Its trade creditors include Peri Formwork Systems Inc. at $526,929.
The officer filed report no. Sixth Report. Able Infrastructure continues operating to complete its remaining contract (the Liam George project) while winding down and monitoring liquidity, whereas Precision Concrete's operations have ceased and are minimal following the transfer of its contracts to Highrise.
Precision Concrete and Bespoke - CCAA Notice to Creditors dated December 5, 2025.pdf — Notice to creditors
Able Infrastructure Inc. and other affiliates including Precision Concrete Services Limited and related holding and operating companies — CCAA filed, Nova Scotia.
Able Infrastructure, Precision Concrete and Bespoke - Creditor Listing.pdf — List of creditors
Undated filings5 — no date appears on the document · show
Case update
Able Infrastructure: the financing for the equipment sale collapses
Able Infrastructure and its co-applicants told Grant Thornton on September 22 that the lender agreement financing the sale of their equipment to two related companies had collapsed. The monitor supports a stay to November 6, and says it will support no further extension unless the sale is finalized and brought to the court for approval.
Precedent note
Reversing the Crown's GST/HST trust
Outside insolvency, the Crown's trust for unremitted GST/HST can rank ahead of a lender's security; a bankruptcy or a CCAA ends that priority. Seven 2026 files show lenders choosing their route, and four show the trust that survives both, for payroll source deductions.
Debtor
Able Infrastructure Inc. and other affiliates including Precision Concrete Services Limited and related holding and operating companies
Monitor
Doane Grant Thornton
Counsel of record
| Party | Counsel | First seen | Source |
|---|---|---|---|
| MonitorDoane Grant Thornton | Stewart McKelvey | 3 Dec 2025 | Service list · 3 Dec 2025 |
| ApplicantAble Infrastructure Inc. Bespoke Canadian Investments Inc. Precision Concrete Services Limited | BoyneClarke LLP | 3 Dec 2025 | Service list · 3 Dec 2025 |
| DebtorAble Infrastructure Inc. and other affiliates including Precision Concrete Services Limited and related holding and operating companies | BoyneClarke LLP | 20 Mar 2026 | Application · 20 Mar 2026 |
| CreditorCansel Survey Equipment Inc | McInnes Cooper | 3 Dec 2025 | Service list · 3 Dec 2025 |
| CreditorMarco Group Limited | Cox & Palmer | 20 Mar 2026 | Application · 20 Mar 2026 |
| CreditorMayabella Properties Limited | McInnes Cooper | 3 Dec 2025 | Service list · 3 Dec 2025 |
| CreditorO'Regan Chevrolet Buick GMC Cadillac Limited O' Regan Motors Limited | McInnes Cooper | 3 Dec 2025 | Service list · 3 Dec 2025 |
| # | Priority class | Creditor | Amount | Source |
|---|---|---|---|---|
| 4 | Secured | Cansel Survey Equipment Inc. · in 3 casesListed under Secured Creditors in Internal Creditor Listing; amount shown as $1, possibly nominal/placeholder — debtor: Able Infrastructure Inc. · as of 25 Nov 2025 | $1 | Able Infrastructure, Precision Concrete and Bespoke - Creditor Listing.pdf |
| 4 | Secured | |||
| 4 | Secured | |||
| 8 | Unsecured | |||
| 8 | Unsecured | |||
| 8 | Unsecured | |||
| 8 | Unsecured | |||
| 8 | Unsecured | |||
| 8 | Unsecured | |||
| 8 | Unsecured |
21 more claims in 2 classes The stack holds Secured and Unsecured claims.
Every creditor and every amount, drawn to scale.
Card required. Nothing charged for 5 days. Cancel anytime.
Already a subscriber? Sign in.
See all plans2 engagements · 1 firm — latest: Stewart McKelvey, 16 Dec 2025 – 13 Mar 2026, in feesFourth Report of the Monitor · 20 Mar 2026
| Firm | Period | Hours | Fees | Rates | Source | ||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Stewart McKelveyCounselperiod 2 of 2 | 16 Dec 2025 – 13 Mar 2026 | 5 people | Fourth Report of the Monitor · 20 Mar 2026 | ||||||||||||||||||||||||||||||||
5 people — Stewart McKelvey, 16 Dec 2025 – 13 Mar 2026 · 15 blurred figures
| |||||||||||||||||||||||||||||||||||
| Stewart McKelveyCounselperiod 1 of 2 | — | 4 people | Fourth Report of the Monitor · 20 Mar 2026 | ||||||||||||||||||||||||||||||||
4 people — Stewart McKelvey · 12 blurred figures
| |||||||||||||||||||||||||||||||||||
33 blurred figures above
What the firm billed, and each person’s hours and rate — each as the filing states it, with its source.
Card required. Nothing charged for 5 days. Cancel anytime.
Already a subscriber? Sign in.
See all plansCash on hand
$256K
As at 26 Jun 2026Sixth Report of the Monitor dated July 10, 2026
| Date | Document | File |
|---|---|---|
Seventh Report of the Monitor dated September 28, 2026
| PDF · Subscribers | |
Affidavit of Ziyad Chediac dated September 23, 2026
| PDF · Subscribers | |
Notice of Motion dated September 23, 2026
| PDF · Subscribers | |
Sixth Report of the Monitor dated July 10, 2026
| PDF · Subscribers | |
| Affidavit of Ziyad Chediac dated July 6, 2026 | PDF · Subscribers | |
| Notice of Motion dated July 6, 2026 | PDF · Subscribers | |
| Written Submission dated July 6, 2026 | PDF · Subscribers | |
| Written Submission | PDF · Subscribers | |
| Fifth Report of the Monitor dated May 27, 2026 | PDF · Subscribers | |
| Affidavit of Ziyad Chediac dated May 25, 2026 | PDF · Subscribers | |
| Written Submission dated May 25, 2026 | PDF · Subscribers | |
| Notice of Motion dated May 22, 2026 | PDF · Subscribers | |
| Draft Order | PDF · Subscribers | |
| Monitor's Book of Authorities | PDF · Subscribers | |
Fourth Report of the Monitor dated March 20, 2026
| PDF · Subscribers | |
| Motion Brief dated March 20, 2026 | PDF · Subscribers | |
Notice of Motion dated March 20, 2026
| PDF · Subscribers | |
| Affidavit of Ziyad Chediac dated March 17, 2026 | PDF · Subscribers | |
| Notice of Motion dated March 17, 2026 | PDF · Subscribers | |
| Third Report of the Monitor dated January 23, 2026 | PDF · Subscribers | |
| Affidavit of Ziyad Chediac dated January 22, 2026 | PDF · Subscribers | |
| Motion dated January 22, 2026 | PDF · Subscribers | |
| Written Submission dated January 22, 2026 | PDF · Subscribers | |
| Second Report of the Monitor dated December 17, 2025 | PDF · Subscribers | |
| Affidavit of Ziyad Chediac dated December 16, 2025 | PDF · Subscribers | |
| Notice of Motion dated December 16, 2025 | PDF · Subscribers | |
| Written Submission dated December 16, 2025 | PDF · Subscribers | |
| Affidavit of Ziyad Chediac dated December 8, 2025 | PDF · Subscribers | |
| Book of Authorities dated December 8, 2025 | PDF · Subscribers | |
| Notice of Motion dated December 8, 2025 | PDF · Subscribers | |
| Written Submission dated December 8, 2025 | PDF · Subscribers | |
| Precision Concrete and Bespoke - CCAA Notice to Creditors dated December 5, 2025.pdf | PDF · Subscribers | |
| Affidavit of Danny Chediac dated December 3, 2025 | PDF · Subscribers | |
| Affidavit of Ziyad Chediac dated December 3, 2025 | PDF · Subscribers | |
| Amended Notice of Motion dated December 3, 2025 | PDF · Subscribers | |
| Book of Authorities dated December 3, 2025 | PDF · Subscribers | |
| First Report of the Monitor dated December 3, 2025 | PDF · Subscribers | |
| Notice of Motion dated December 3, 2025 | PDF · Subscribers | |
Service List as of December 3, 2025
| PDF · Subscribers | |
| Written Submissions dated December 3, 2025 | PDF · Subscribers | |
| Able Infrastructure -CCAA Notice to Creditors dated November 27, 2025 | PDF · Subscribers | |
| Pre-filing Report of the Proposed Monitor dated November 27, 2025 | PDF · Subscribers | |
Able Infrastructure, Precision Concrete and Bespoke - Creditor Listing.pdf
| PDF · Subscribers | |
| Draft Interim Fees & Activities Approval Order.pdf | PDF · Subscribers | |
| Affidavit Ziyad Chediac dated November 14, 2025 | PDF · Subscribers | |
| Affidavit of Danny Chediac dated November 14, 2025 | PDF · Subscribers | |
| Notice of Application dated November 14, 2025 | PDF · Subscribers | |
| Written Submission dated November 14, 2025 | PDF · Subscribers | |
| Book of Authorities | PDF · Subscribers | |
| Draft Stay Extension Order | PDF · Subscribers | |
| Draft of Second Amended ARIO | PDF · Subscribers | |
Draft of Second Amended ARIO (Redline)
| PDF · Subscribers | |
Redline of Draft Amended and Restated Initial Order
| PDF · Subscribers | |
Filing titles and dates are public, and so is each filing's own page. The figures read from them are for subscribers.
CiteProceedings., “Able Infrastructure Inc. and other affiliates including Precision Concrete Services Limited and related holding and operating companies” (CCAA), Supreme Court of Nova Scotia. Retrieved 4 November 2026, https://proceedings.ca/case/able-infrastructure-inc-and-other-affiliates-including-precision-concrete-servic