Victoria Gold: C$40 million in cash, C$100 million on permits and production

PwC's December 2 motion asks the court to approve a reverse vesting deal making a Boroo subsidiary Victoria Gold's sole shareholder for up to C$140 million, C$100 million of it due on restart permits and production. Without permits four years after closing, subject to extension, Boroo could return the company and recover up to C$55 million.

Proceedings. · · 10 min read

PricewaterhouseCoopers Inc., receiver of Victoria Gold Corp., is asking the Ontario Superior Court of Justice (Commercial List), in a motion returnable December 2, to approve a subscription agreement signed on October 20 under which Gatsuurt Mining Inc., a wholly owned subsidiary of Boroo Pte. Ltd., would become the sole shareholder of the company that owns the Eagle Gold Mine. The structure is a reverse vesting order: Gatsuurt would subscribe for new shares, all existing equity would be cancelled for no consideration, and the assets and liabilities the deal leaves behind would vest in a new ResidualCo, which would replace Victoria Gold as respondent in the receivership, per the Notice of Motion, Nov. 18, 2026, paras. 1(a)–(f), 16.

The price is up to C$140 million, of which C$40 million is cash: a C$20 million deposit due within two business days of the approval order becoming final, and C$20 million at closing. The other C$100 million comes in two payments of C$50 million, one when the permits needed to restart the mine are in place and one when it reaches commercial production. The capital needed to remediate the mine, obtain the permits and restart operations "proved to be materially greater than originally anticipated," the report says, a scale Boroo advised became clearer as it developed its restart plan; Boroo now intends to spend approximately C$800 million between 2027 and 2029 and expects to commit more than C$1.5 billion in all. Those requirements, the receiver writes, "are a key factor affecting the value of the Victoria Gold Assets, and contributed to the Transaction being structured with a significant portion of the consideration deferred," per the Eleventh Report of the Receiver, Nov. 18, 2026, paras. 45–46, 53.

The mine is approximately 375 kilometres north of Whitehorse, in the traditional territory of the First Nation of Na-Cho Nyäk Dun. On June 24, 2024 its heap leach facility failed, releasing approximately two million tonnes of cyanide-contaminated ore material into the environment, and the Government of Yukon applied for the receivership that followed, per the Notice of Motion, Nov. 18, 2026, paras. 4–8. The emergency works are complete to Yukon's satisfaction, the report says, and until closing the site stays in care and maintenance. Boroo's exclusivity, extended in July as reported here on September 17, was to end on October 20, the agreement's date, per the Eleventh Report of the Receiver, Nov. 18, 2026, paras. 3–4, 20–21, 39.

Fifty-nine bidders called, one left

The sale process, run since June 2025 by BMO Nesbitt Burns Inc. as the receiver's financial advisor, contacted 59 potential bidders; 14 parties signed non-disclosure agreements. Three submitted letters of intent by September 9, 2025, a fourth sent one later, and all four went into Phase 2. After three refreshed non-binding proposals in December 2025, two of those bidders met separately in Whitehorse in February 2026 with Yukon, as regulator, and non-technical representatives of the First Nation. "Following these meetings," the report says, "Boroo emerged as the sole Qualified Bidder seeking to progress to the next phase of the Victoria Gold Sale Process." The receiver calls the result "the only viable transaction that emerged from the Victoria Gold Sale Process," per the Eleventh Report, Nov. 18, 2026, paras. 26, 28–31, 33–35, 43.

The deposit, and two milestones

The deposit is non-refundable, the report says, unless Gatsuurt terminates before closing for an uncured material violation or breach by the receiver. The permit milestone is, in the report's summary, generally the date on which each restart permit, including the required Quartz Mining Licence and Water Licence amendments, has been issued or amended, is in full force and is no longer subject to appeal or challenge, and the existing permits needed for the restart plan remain in force. Commercial production falls on the last day of the first 30 consecutive days after the restart throughout which the mine's recovery plant has processed solution from new ore at an average of at least 29,520 cubic metres a day, 60% of its nameplate capacity. The receiver notes that the permit milestone is expected approximately two to four years after closing, and commercial production 18 to 24 months after that, per the Eleventh Report, Nov. 18, 2026, para. 53.

Gatsuurt "shall cause the Company to pay to the Receiver" each C$50 million instalment, per the Subscription Agreement, Oct. 20, 2026, s. 2.3(a). Boroo's guarantee of Gatsuurt's obligations is unsecured; after closing Victoria Gold itself would guarantee the deferred payments up to C$100 million plus enforcement costs, secured on its tangible mining assets but behind Yukon's security for a promissory note of up to C$104,162,162 and any future arm's-length lender financing the mine. The outside date is the later of December 31, 2026 and January 4, 2027. Gatsuurt may terminate before closing if there is, among other events, "a further significant failure, slide or loss of containment at the Leach Pad," per the Eleventh Report, Nov. 18, 2026, para. 53.

A way back out

The exit right sits in a framework agreement among Boroo, Gatsuurt, Yukon and Victoria Gold, also dated October 20, that takes effect at closing. If the permit milestone has not occurred by the fourth anniversary of closing, or an application for a restart permit has before then been finally refused, "in each case despite reasonable commercial efforts by the Boroo Parties," they "shall be entitled, exercisable in their sole discretion, to abandon or otherwise exit the Site …" Regulatory delay can extend the four years by up to 12 months in all, per the Framework Agreement, Oct. 20, 2026, ss. 5.1, 5.3. For the exit right, permits issued on terms that do not legally permit heap leach mining as the restart plan contemplates, or would reasonably be expected to make it technically infeasible, leave the milestone deemed unmet, unless a deficient application is the cause, per the Eleventh Report, Nov. 18, 2026, paras. 53–54.

As the report summarizes the conditions, Boroo must have filed the required permit applications within two years of closing and met other permit application milestones, must not be in uncured material default and must give at least 90 days' notice, and an independent expert selected by Yukon must certify that prescribed site conditions are met. On a valid exit the deferred consideration falls to zero, Gatsuurt transfers all of Victoria Gold's shares to ResidualCo or as the receiver, with Yukon's consent, directs, and the reclamation security is released, per the Eleventh Report, Nov. 18, 2026, para. 55(d). In exchange the receiver pays Gatsuurt, "from the property of the receivership estate only," the subscription price less the deposit, plus all costs Victoria Gold or Gatsuurt incurred at the mine after closing, to a maximum of C$55 million, per the Subscription Agreement, Oct. 20, 2026, s. 2.5(a).

That is "up to $15 million more than the $40 million of Closing Cash Consideration paid to the receivership estate (before interest earned on the Exit Reserve)," the receiver writes. The exit right "was a critical term of achieving a deal with Boroo," it says, and the report estimates that by the four-year mark Boroo will have spent the majority of the approximately C$800 million it intends to spend, per the Eleventh Report, Nov. 18, 2026, paras. 55(d), 59. The order sought would have the receiver hold C$20 million of the closing cash in a segregated, interest-bearing exit reserve, beside undrawn availability under Yukon's facility or other estate funds, and would rank Gatsuurt's rights in those amounts "in priority to the claims of any other Person, subject only to the Receiver's Charge in the case of the Other Amounts," for as long as the exit obligation is outstanding, per the draft Approval and Reverse Vesting Order, Tab 5, paras. 28–29 and the Eleventh Report, Nov. 18, 2026, para. 57. That ranking puts them ahead of Yukon's own borrowings charge, the report notes, and Yukon, as lender, has consented. The receiver says the priority will not unfairly prejudice creditors because, "absent the Transaction, there is no realistic prospect of recovery for any creditors," per the Eleventh Report, Nov. 18, 2026, para. 60(c), (e).

Keep reading with a 5-day free trial

About 5 more minutes of this analysis, and 4 more sections. Every fact in it cites the filing it was read from.

Start 5-day trial

Card required. Nothing charged for 5 days. Cancel anytime.

Already a subscriber? Sign in.

See all plans⁠

Analysis is editorial; every factual claim cites the record. The record itself never editorializes.

Facts and summaries are extracted automatically from the court filings linked on each page; the filings remain the authoritative record. Suggested corrections are reviewed against the source filings.