CYMI Canada Inc.'s proposal to its creditors is dated November 11, 2026, the last day of the time the court had given it to make one, per the Order, Oct. 2, 2026, para. 4. It rests on two receivables, the first a construction holdback on the Finch West LRT, which Mosaic Transit Constructors General Partnership still held when the proposal was signed. The other is a contingent claim against Signature on the Saint Lawrence Construction G.P. (SSLC) for CYMI's work on the reconstruction of the Champlain Bridge, whose net amount the proposal's waterfall schedule puts at anywhere from $0 to $11,397,000 and which, it says, "is not likely to be collected before 2029 according to SSLC," per the Proposal of CYMI Canada Inc., Nov. 11, 2026, s. 1.1 ("Mosaic Holdback", "SSLC"), s. 2.1(d), (f) and Sched. "A". Creditors are to meet on December 2 to vote on it, per the Notice of Proposal to Creditors (Form 92), Nov. 16, 2026, p. 1.
The proposal says the dispute over the first has been settled. Under an agreement made with Mosaic on October 16, the $4,988,976.22 holdback, HST included, is to be paid over to CYMI or its lawyers in trust, and $500,000 of it held by CYMI through its lawyers until November 12, 2027, the end of the warranty period under the Mosaic contract, to fund the cost of valid warranty claims. The waterfall schedule says the reserve was "Created further to agreement with Mosaic which is documented by email," and on November 11 it marked the holdback "Not yet received." The application CYMI brought in September to make Mosaic pay "is presently paused due to the Mosaic Settlement" and will be restarted if Mosaic does not follow through, per the Proposal, s. 1.1 ("Mosaic Holdback"), s. 2.1(a), (c) and Sched. "A". When the case was last reported here, on September 17, CYMI was asking the Commercial List for a timetable; Mosaic had requested "a warranty bond in the amount of $5,000,000.00," according to a March 2 letter from CYMI's lawyers, per the Motion Record, Aug. 18, 2026, Ex. "G", p. 274.
From a timetable to a settlement
Justice Dunphy's endorsement of September 17 set out what was in issue. "It appears that there is no dispute as to the amount of the holdback…," the judge wrote; the issue was "whether, as Mosaic contends, the contract between itself and the debtor requires the posting of additional security." The parties had agreed to an expedited schedule, per the Endorsement of Justice S. Dunphy, Sept. 17, 2026, paras. 1–2. The order set a two-hour hearing for November 12 by videoconference, per the Order, Sept. 17, 2026, para. 2(e). No order from that date is in the record.
A settlement was what CYMI had told the court it hoped for. Its sole director's affidavit of September 30 said the proposal concept "would ideally avoid litigation over the holdback via a settlement with Mosaic to release the holdback in return for assurance that CYMI Canada is able to continue its warranty fulfilment and fund its warranty obligations and setting a reserve to fund same," per the Affidavit of CYMI's sole director, Sept. 30, 2026, para. 19(i). On October 2 Justice Cavanagh granted what the endorsement calls "a final extension of its BIA stay" to November 11, writing that the extra time would let CYMI "formulate a proposal that offers a materially better outcome than a bankruptcy," per the Endorsement of Justice Cavanagh, Oct. 2, 2026, paras. 4–6 and the Order, Oct. 2, 2026, para. 4. The proposal trustee, TDB Restructuring Limited, had told the court it was the final extension available under s. 50.4(9) of the Bankruptcy and Insolvency Act, per the Fourth Report of the Proposal Trustee, Sept. 30, 2026, para. 43.
The proposal's structure had moved along the way. In July CYMI's affidavit anticipated a proposal premised on realizing its principal assets "together with a deferral of a portion of the unsecured pre-filing intercompany claims of CYMI Spain (this is still being negotiated)," per the Second affidavit of CYMI's sole director, July 2, 2026, para. 28. On September 30 the sole director said the structure and scope of any sponsorship by the parent "presently depends upon greater certainty regarding the BNA claim and the Mosaic recovery," per the Affidavit, Sept. 30, 2026, para. 17. The proposal as filed contains no term deferring or subordinating any claim.
Where the holdback goes
The proposal would spend the holdback in a set order. After the $500,000 warranty reserve would come a $750,000 administration reserve, held by CYMI or, at its option, by the trustee, "to fund the ongoing operation of the Company pending the completion of all aspects of this Proposal," including the work of CYMI, the trustee and their counsel, collection of the Champlain receivable and the effort to reverse a reassessment by the Canada Revenue Agency; CYMI may release any excess for distribution, with the trustee's approval. The balance would pay the priority claims, the construction trust claims among them, along with the HST portion of the holdback payable to the CRA and amounts owing to the DIP lender, the trustee and its lawyers and CYMI's lawyers, per the Proposal, s. 2.1(b)–(c), s. 4.1.
Schedule B lists the trust claims to be paid from the holdback once collected: Barton Malow Canada Ltd., formerly Alltrade Industrial Contractors Inc., $1,272,428.66; ABB Inc., $573,634.33; and SICE Canada Inc., $41,967.36, plus where applicable interest and other costs "to the extent permitted by law," per the Proposal, Sched. "B". In September the trustee reported that Barton Malow had agreed for the time being to refrain from enforcement while CYMI pursued a proposal, per the Fourth Report, para. 32.
The waterfall schedule puts the HST component at $502,000, rounded, "Proposed to be remitted to CRA once Mosaic Holdback collected." CYMI intends to object to a further reassessment of approximately $217,000, an objection it believes "ought to be allowed once it pays the Trust Claims via this Proposal," per the Proposal, s. 2.1(iv) and Sched. "A". It has until December 1 to object, the trustee reported, per the Fourth Report, para. 31. CYMI "does not believe it has any secured creditors," per the Proposal, s. 2.4.
Schedule A then adds the reserves and payments to $3,640,000, rounded, and shows $1,348,000 as the net available for interim distribution to creditors, marked "estimate/rounded." A note says the schedule is meant "to illustrate the structure of the waterfall; not what will be actually received or disbursed by CYMI nor what will actually be received by creditors under the Proposal," per the Proposal, Sched. "A" and note 1. The initial dividend is to be paid pro rata to proven ordinary claims from the "Net Surplus of the Mosaic Holdback" forthwith after that surplus has been determined, net of the Superintendent's levy, per the Proposal, s. 4.2(a), s. 4.3(e).
Champlain, in 2029 or by sale
A final distribution waits on the Champlain receivable; the waterfall schedule also lists any unused balances of the two reserves as potentially available later. The proposal describes the 2020 contract with SSLC as one that quantified what remained owing to CYMI, "established the sum of CAD $11,397,293.24 as upper limit payable to CYMI," and set a formula that reduces the amount payable pro rata according to SSLC's recovery in its pending litigation against the Government of Canada as project owner, "which litigation is projected by SSLC to go to trial in 2029." The net proceeds, after the priority claims and costs then outstanding, would go to unsecured creditors in a final pro rata distribution "once the SSLC Net Amount has been collected (if anything is collected on same) and quantified," per the Proposal, s. 1.1 ("SSLC Contract"), s. 2.1(d), s. 4.2(b). In September the trustee understood there had been no material developments on the receivable since its August report, per the Fourth Report, para. 28.
Keep reading with a 5-day free trial
About 4 more minutes of this analysis, and 3 more sections. Every fact in it cites the filing it was read from.
Card required. Nothing charged for 5 days. Cancel anytime.
Already a subscriber? Sign in.
See all plans