British Columbia · CCAA
Seventh Report of the Monitor dated May 4, 2026
Court officer report · 4 May 2026
What we verified from this filing5 verified
- report date4 May 2026
- report noSeventh Report
- operational summaryAs at the date of this Seventh Report, the Monitor, for and on behalf of the Debtors, has borrowed $18,661,750 under the Interim Financing Facility to complete construction of the Eclipse Project and administer these proceedings. Unit Transactions began closing on April 27, 2026, and as of May 1, 2026, a total of 66 Pre-Sale Units have closed, with a further 123 Unit Transactions scheduled to close by May 11, 2026.
- professional feesamount: 1380858 · currency: CAD
- receipts cumulativeamount: 46683684 · currency: CAD