British Columbia · CCAA
Fifth Report of of the Monitor dated December 8, 2025
Court officer report · 8 December 2025
A plain-language read of this filing opens with a subscription.
What we verified from this filing6 verified
- report date8 December 2025
- report noFifth Report
- operational summaryConstruction at the Eclipse Project has moved into its final stages, with work focused on completing remaining Units, finalizing building systems, and preparing the building for occupancy; final occupancy and Pre-Sale Purchaser turnover expected end of January or early-February 2026, subject to typical construction variables and potential unforeseen delays including the Fire Alarm Tie-in.
- cash on handamount: 10027 · currency: CAD
- professional feesamount: 0 · currency: CAD
- receipts cumulativeamount: 9005045 · currency: CAD