Gabriel Construction Ltd., Gabriel Construction (Alberta) Ltd and SaskAlta Environmental Solutions Inc. have been the subject of a court-appointed receivership commenced on March 21, 2017, grounded in section 243 of the Bankruptcy and Insolvency Act together with provincial Judicature Act jurisdiction. The proceeding was brought in Alberta, in what was then the Court of Queen's Bench of Alberta and is now the Court of King's Bench of Alberta, under court file number 1701-03799. The three related debtors were administered together in the one proceeding, which is now closed.
Receiver’s Final Report pursuant to subsection 246(3) – dated November 20, 2020 — Court officer report
Application for Final Distribution and Discharge of the Receiver - filed Oct. 1, 2020 — Application / notice of application
Application in relation to the Honduras Property – filed August 22, 2017 — Application / notice of application
Notice and Statement of the Receiver - Gabriel Construction Ltd., dated March 31, 2017 — Notice to creditors
Receivership order placed all three companies under a court-appointed receiver, commencing the Alberta proceedings under BIA s. 243 and provincial Judicature Act authority in court file 1701-03799.
Debtor
Gabriel Construction Ltd., Gabriel Construction (Alberta) Ltd and SaskAlta Environmental Solutions Inc.
Receiver
Deloitte
Bench
| Judge | Court | On this docket | Cases on record |
|---|---|---|---|
| Justice Campbell | Court of King's Bench of Alberta | 3 orders, Jun 2017 – Jun 2018 | 43 cases on record |
| Justice Jones | Court of King's Bench of Alberta | 2 orders, Mar 2017 – Oct 2020 | 93 cases on record |
Counsel of record
| Party | Counsel | First seen | Source |
|---|---|---|---|
| ReceiverDeloitte | Torys LLP | 7 Jun 2017 | Service list · 7 Jun 2017 |
| DebtorGabriel Construction Ltd., Gabriel Construction (Alberta) Ltd and SaskAlta Environmental Solutions Inc. | Borden Ladner Gervais LLP · Field Law | 21 Mar 2017 | Order · 6 Sep 2017 |
| CreditorContech Electric Ltd | Drieseen De Rudder LLP | 7 Jun 2017 | Service list · 7 Jun 2017 |
| CreditorRoyal Bank of Canada | Borden Ladner Gervais LLP | 7 Jun 2017 | Service list · 7 Jun 2017 |
| CreditorTown of Westlock and Westlock Regional Water Services Commission | McLennan Ross LLP | 7 Jun 2017 | Service list · 7 Jun 2017 |
Unsecured creditors: no distribution. Canada Revenue Agency paid in full · Royal Bank of Canada short · Service Canada paid in full.FinalReceiver’s Final Report pursuant to subsection 246(3) · 20 Nov 2020
| Class | Creditor | Claims | Recovery | Basis | Source |
|---|---|---|---|---|---|
| Deemed trust | Canada Revenue Agency | — | paid in full | Finalper the receiver | Receiver’s Final Report pursuant to subsection 246(3) · 20 Nov 2020 |
| Secured | Royal Bank of Canada | — | shortfall | Finalper the receiver | Receiver’s Final Report pursuant to subsection 246(3) · 20 Nov 2020 |
| Preferred | Service Canada | — | paid in full | Finalper the receiver | Receiver’s Final Report pursuant to subsection 246(3) · 20 Nov 2020 |
| Preferred | Workers' Compensation Board | — | paid in full | Finalper the receiver | Receiver’s Final Report pursuant to subsection 246(3) · 20 Nov 2020 |
| Unsecured | Companies' unsecured creditors | — | no distribution | Finalper the receiver | Receiver’s Final Report pursuant to subsection 246(3) · 20 Nov 2020 |
Each row is one filing's statement, copied as it reads and never computed. "Estimated" is the officer's forecast; "Under the plan" is the plan's or proposal's own term; "Final" is a declared or paid distribution; a row with no chip states no footing. A range is the two numbers stated; "of proven claims" is the document's own denominator.
3 blurred figures above
The claims and what each class or creditor recovers — each as the filing states it, with its source.
Card required. Nothing charged for 5 days. Cancel anytime.
Already a subscriber? Sign in.
See all plans2 engagements · 2 firms — latest: Deloitte Restructuring Inc., 21 Mar 2017 – 18 Sep 2020, in feesFourth Report of the Receiver - filed Oct. 1, 2020 · 1 Oct 2020
| Firm | Period | Hours | Fees | Rates | Source |
|---|---|---|---|---|---|
| Deloitte Restructuring Inc.Receiver | 21 Mar 2017 – 18 Sep 2020 | — | not stated | Fourth Report of the Receiver - filed Oct. 1, 2020 · 1 Oct 2020 | |
| Torys LLPCounsel to the receiver | 21 Mar 2017 – 15 Sep 2020 | — | not stated | Fourth Report of the Receiver - filed Oct. 1, 2020 · 1 Oct 2020 |
2 blurred figures above
What each firm billed — each as the filing states it, with its source.
Card required. Nothing charged for 5 days. Cancel anytime.
Already a subscriber? Sign in.
See all plans| Date | Document | File |
|---|---|---|
| Affidavit confirming discharge of Receiver – dated November 23, 2020 | PDF · Subscribers | |
Receiver’s Final Report pursuant to subsection 246(3) – dated November 20, 2020
| PDF · Subscribers | |
Final Distribution and Receiver’s Discharge order – filed October 22, 2020
| PDF · Subscribers | |
Application for Final Distribution and Discharge of the Receiver - filed Oct. 1, 2020
| PDF · Subscribers | |
Fourth Report of the Receiver - filed Oct. 1, 2020
| PDF · Subscribers | |
Approval and Vesting Order , filed June 26, 2018
| PDF · Subscribers | |
| Application for an Approval and Vesting Order and a Restricted Court Access Order – filed June 12, 2018 | PDF · Subscribers | |
Third Report of the Receiver – filed June 12, 2018
| PDF · Subscribers | |
Consent Order – filed September 6, 2017
| PDF · Subscribers | |
| Affidavit of Tracey Hutchings – sworn and filed August 31, 2017 | PDF · Subscribers | |
| Application in relation to the Honduras Property – filed August 22, 2017 | PDF · Subscribers | |
| Second Report of the Receiver – filed August 22, 2017 | PDF · Subscribers | |
Approval of Auction Proposal Distribution of Funds Order - granted June 7, 2017
| PDF · Subscribers | |
Letter to Service List re Application on June 7, 2017
| PDF · Subscribers | |
Restricted Court Access Order - granted June 7, 2017
| PDF · Subscribers | |
| Application for Order Approving Auction Proposal, Distribution of Funds, Restricted Court Access Order - filed June 1, 2017 | PDF · Subscribers | |
| First Report of the Receiver - filed June 1, 2017 | PDF · Subscribers | |
| Notice and Statement of the Receiver - Gabriel Construction (Alberta) Ltd., dated March 31, 2017 | PDF · Subscribers | |
| Notice and Statement of the Receiver - Gabriel Construction Ltd., dated March 31, 2017 | PDF · Subscribers | |
| Notice and Statement of the Receiver - SaskAlta Environmental Solutions Inc., dated March 31, 2017 | PDF · Subscribers | |
Receivership Order granted March 21, 2017
| PDF · Subscribers | |
Filing titles and dates are public, and so is each filing's own page. The figures read from them are for subscribers.
CiteProceedings., “Gabriel Construction Ltd., Gabriel Construction (Alberta) Ltd and SaskAlta Environmental Solutions Inc.” (Receivership (court-appointed)), Court of King's Bench of Alberta. Retrieved 4 November 2026, https://proceedings.ca/case/gabriel-construction-ltd-gabriel-construction-alberta-ltd-and-saskalta-environme