What we verified from this filing15 verified
- report noFourth
- operational summarySince the Monitor’s Third Report, the CCAA Parties have implemented various restructuring measures with the assistance of the Monitor, including receiving remaining super modules and truckable modules from China essential to the Biorefinery, securing an amended payment schedule with Hydro-Quebec for the 230kV power line commissioning rescheduled to late September 2025, performing project demobilization and asset preservation for non-critical path components, stabilizing operations through stakeholder engagement, advancing the Court-approved SISP, conducting negotiations with Conceptum USA, issuing stay notices to subcontractors, and reviewing cash flows and funding requests.
- report date11 August 2025
- cash on handamount: 5531000 · currency: CAD
- professional feesamount: 2979000 · currency: CAD
- receipts cumulativeamount: 223000 · currency: CAD
- cash on handnote: Opening cash balance on July 26, 2025; the Updated Cash Flow Forecast projects a positive cash balance of $0.6M on October 3, 2025 (a forecast, not a position). The variance table shows a closing cash balance of $5,531K (in '000$) at July 25, 2025. · as at: 2025-07-26 · amount: 5500000 · currency: CAD
- disbursementsnote: Actual total disbursements of (22 212) in '000$ CAD versus forecast (23 108); this is a period figure for the 8-week comparison, not a figure cumulative since the filing date. · since: 8 weeks ended July 25, 2025 (May 31, 2025 to July 25, 2025) · amount: 22212000 · currency: CAD
- operational summaryThe CCAA Parties are still in the construction phase of the Project with no ability to generate income. They are continuing critical-path work (module delivery, Hydro-Québec power line, electrolyzer preparation) while preserving non-critical components, running the SISP (binding offers received August 7, 2025), and funding operations through interim financing.
- professional feesnote: Actual professional fees disbursed of (2 979) in '000$ CAD versus forecast (3 279); the report does not separately state the Monitor's own fees or whether tax is excluded. · party: Professional fees (all professionals) per the actual-vs-forecast cash flow variance table · amount: 2979000 · period: 8 weeks ended July 25, 2025 · currency: CAD
- receipts cumulativenote: Total receipts of 223 (in '000$ CAD) are 'Other receipts' only; Interim Facility advances of $9.2M are shown separately as draws, not as receipts. · since: 8 weeks ended July 25, 2025 (May 31, 2025 to July 25, 2025) · amount: 223000 · currency: CAD
- report date11 August 2025
- report noFourth Report
- sale advisorBarclays
- sale outcometext: SISP ongoing; Binding Offers received and under review by the Monitor as of the report · scope: whole_business · status: pending_approval