Edge on Triangle Park Inc. et al.
Follow- Proceeding
- CCAACompanies' Creditors Arrangement Act, R.S.C. 1985, c. C-36, as amended
- File
- CV-16-11541-00CL
- Industry
- Real estate · Residential development
Edge on Triangle Park Inc. et al. obtained protection under the Companies' Creditors Arrangement Act by an initial order made on 6 October 2016 in the Ontario Superior Court of Justice, on the application of Urbancorp Cumberland 2 GP Inc., Urbancorp Cumberland 2 L.P., Bosvest Inc., Edge on Triangle Park Inc. and Edge Residential Inc. The Fuller Landau Group Inc. acts as monitor. The largest unsecured claims stated are $1,907,098.81 to Urbancorp Toronto Management Inc. and $328,591.10 to 1388 Successful Ventures Ltd.
A claims procedure has been established — see the order for deadlines.
Per the Claims Procedure Order dated 27 February 2019.
Reported distributions totalling $3,264,743 to unsecured creditors with proven claims of $22,661,197.95, and $7,810,787 held in the Monitor's trust account before the late July 2023 distribution.
Reported that Westside's June 2021 distribution paid the City of Toronto's secured claim in full and 56% of unsecured claims, bringing cumulative unsecured payment to just over 81%.
Source: 40th Report of the Monitor
Reported Monitor's fees of $72,463.17 and GSNH's $61,156.73 for 1 November 2021 to 31 January 2022, and a planned $3,000,000 pro rata unsecured distribution on closing of the Edge Space transaction.
Approved the 19 November 2021 agreement of purchase and sale with 2509489 Ontario Inc. for the Edge Space, residential unit 1210E and seven parking spots, the price sealed.
Source: Order of Chief Justice G.B. Morawetz dated December 3 2021
Reported that TSCC 2448's new secured claim left the Monitor unable to fix the reserve for secured claims, deferring the $3.5 to $4 million unsecured distribution previously anticipated.
Recorded receipt of the geothermal settlement proceeds from KSV and distribution of $5,476,716 to the 14 accepted Lien and Trust Claimants, with Westside interim distributions of $1,236,163.
Reported $6,408,418 in the combined accounts at 19 May 2021 and projected, subject to approval of a geothermal proceeds settlement, payment in full of construction lien and trust claimants and a rateable unsecured distribution.
Addressed the disputed Dolvin claims process in the Westside estate, recommending disallowance of the remaining $274,025.00 of Dolvin's trust claim so administration could proceed.
Approved the sales process described in the Twenty-Ninth Report for the vacant residential condominium units at 36 Lisgar Street, Toronto, including associated parking spaces and lockers.
Source: Order of Chief Justice Morawetz
Reported $6,256,219.39 combined in the Consolidated Bankruptcy and LP CCAA accounts at 27 July 2020 and proposed paying $72,949.42 to Lien Claimants and $1,697,978 pro rata to admitted Trust Claims.
Motion Record - Monitor's Twenty-Sixth report February 20, 2020 — Application / notice of application
Reported continued wind-down of the Cumberland 2 Group: condominium units and Westside parking spots for sale, Tarion/TSCC 2448 warranty claims and the B19 report, with reserves preventing any interim creditor distribution.
Source: Monitor's Twenty-Sixth Report
Updated the status of the Construction Act trust appeal over condominium sale proceeds and sought approval of the Monitor's and its counsel's fees.
Source: Monitor's Twenty-Second Report Supplement - November 26 2019
Motion Record - Monitor's Twenty-Second Report Supplement - November 26 2019 — Application / notice of application
Reported three remaining Triangle condominium units and Westside's 56 parking spots for sale, claims adjudication and Tarion/TSCC 2448 deficiency talks, with funds reserved pending the Court of Appeal construction trust decision.
Source: Monitor's Twenty Fifth Report
Motion Record - Monitor's Twenty-Fifth Report - November 20 2019 — Application / notice of application
An order was granted on 27 September 2019 in the CCAA proceedings before the Ontario Superior Court of Justice (Commercial List).
Source: Order of Justice Morawetz (Approval of Sale of Unit 216) - September 27 2019
Endorsement of Justice Morawetz (Approval of Sale of Unit 216) - September 27 2019 — Endorsement / reasons
Motion Record - Monitor's Twenty Fourth Report - September 23 2019 — Application / notice of application
Endorsement of Chief Justice Morawetz (Stay Extension and directions re. Epic) - August 27 2019 — Endorsement / reasons
Restated, as at 21 August 2019, that Affinity had been paid in full by Edge and was not a creditor in the proceeding.
Source: Monitor's Twenty-Third Report
Reported progress on remaining Triangle units and Westside parking spots, severance and marketing of the Edge Space, the Tarion Bulletin 19 report and TSCC 2448 conciliation, and the consolidated bankruptcy estate.
Source: Monitor's Twenty-Second Report
Reported closing bank positions at 11 May 2019, including Cumberland 2 LP at $3,745,290 and Westside at $1,089,701, and stated Affinity was paid in full by Edge.
Source: Monitor's Twenty-First Report
Reported Triangle and Residential assigned into bankruptcy, the Monitor selling the last condominium and parking units, severing and marketing the Edge commercial space, and pursuing an accounting from Epic/Plazacorp.
Source: Monitor's Twentieth Report
Approved the sale of unit 216 described in the Twenty-Fourth Report and sealed Confidential Appendix 'A', and prospectively approved future sales of individual parking spots at 150 and 170 Sudbury Street.
Source: Approval and Vesting Order
Reported Triangle's sales proceeds account at $392,039.34 and Residential's at $5,820,514.51 as at 9 February 2019, with four Triangle units left, Edge Space severance underway and bankruptcy assignments in preparation.
Source: Monitor's Nineteenth Report
Gave closing bank positions at 10 November 2018 — Triangle $183,813, Residential $32,051, Bosvest $5,488 — and noted Westside, added 25 October 2018, would list its 57 parking spots.
Source: Monitor's Eighteenth Report
Book of Authorities of Guy Gissin and Tarion Warranty Corporation — Application / notice of application
Reported sales of 32 residential units, 5 retail units, 7 parking spots and 4 storage units, proceeds repaying the DIP facility; the contested bankruptcy assignment motion was adjourned to 27 November 2018.
Motion Record - Second Supplement to Monitor's Seventeenth Report — Application / notice of application
Addressed Westside Gallery Lofts Inc., the affiliate proposed to be added: no employees or operations, disbursements limited to professional fees funded from cash on hand, with a creditor list as at 20 September 2018.
Motion Record - Supplement to Monitor's Seventeenth Report — Application / notice of application
Monitor reported substantially all condominium units sold, with five residential units, nine parking spots and eighteen storage units left, and proposed bankrupting Triangle and Residential and bringing Westside under CCAA protection.
Source: Monitor's Seventeenth Report
Responding Written Submissions of the Edge Companies and Alan Saskin — Response / objection pleading
Motion Record of the Foreign Representative - Returnable January 22, 2018 — Application / notice of application
Responding Motion Record of Cooltech, October 31, 2017 - Volume 1 of 2 — Response / objection pleading
Responding Motion Record of Cooltech, October 31, 2017 - Volume 2 of 2 — Response / objection pleading
Responding Motion Record of the Canada Revenue Agency dated September 26, 2017 — Response / objection pleading
A further order granted a week after the 16 December approval and vesting orders, in the CCAA proceedings before the Commercial List.
Approved the sale of the purchased assets to 2494651 Ontario Inc. under sale agreements dated 21 October 2016, vesting on delivery of the Monitor's certificate.
Approved a sale to Edland Realty Corporation under a sale agreement dated 27 October 2016, the agreement filed as a confidential appendix with the price sealed.
A second order of the same date approved Edland Realty Corporation's purchase of the assets described in Schedule 'A', vesting on delivery of the Monitor's certificate.
The initial order made on Thursday, 6 October 2016 placed the applicants under the protection of the Act.
The court granted the initial order under the Companies' Creditors Arrangement Act on October 6, 2016, appointing The Fuller Landau Group Inc. as monitor.
Source: Initial Order
Application Record - Returnable October 6, 2016 - Part 2 — Application / notice of application
Application Record - Returnable October 6, 2016 - Part 4 — Application / notice of application
Book of Authorities - Returnable October 6, 2016 - Part 4 — Application / notice of application
Book of Authorities - Returnable October 6, 2016 - Part 1 — Application / notice of application
Application Record - Returnable October 6, 2016 - Part 1 — Application / notice of application
Application Record - Returnable October 6, 2016 - Part 3 — Application / notice of application
Order made while the applicants were proceeding under Notices of Intention, with The Fuller Landau Group Inc. acting as proposal trustee, before CCAA protection was granted that October.
Source: Order of Justice Hainey
Edge Residential Inc. filed its notice of intention under the Bankruptcy and Insolvency Act, commencing the proceeding.
Undated filings1 — no date appears on the document · show
Debtor
Bosvest Inc.
Debtor
Edge Residential Inc.
Debtor
Edge on Triangle Park Inc.
Debtor
Urbancorp Cumberland 2 GP Inc.
Debtor
Urbancorp Cumberland 2 L.P.
Debtor
Westside Gallery Lofts Inc
Monitor · Proposal trustee
Fuller Landau
Bench
| Judge | Court | On this docket | Cases on record |
|---|---|---|---|
| Justice Morawetz | Ontario Superior Court of Justice | 26 orders, Feb 2019 – Apr 2026 | 141 cases on record |
| Justice Myers | Ontario Superior Court of Justice | 7 orders, Sep 2017 – Feb 2019 | 117 cases on record |
| Justice Newbould | Ontario Superior Court of Justice | 7 orders, May 2016 – Dec 2016 | 111 cases on record |
| Justice Hainey | Ontario Superior Court of Justice | 5 orders, Aug 2016 – Feb 2018 | 211 cases on record |
| Justice Penny | Ontario Superior Court of Justice | 2 orders, Jul 2016 | 196 cases on record |
Counsel of record
| Party | Counsel | First seen | Source |
|---|---|---|---|
| MonitorKSV Kofman Inc | Davies Ward Phillips & Vineberg LLP | 3 Oct 2017 | Service list · 3 Oct 2017 |
| Proposal trustee | Dentons Canada LLP | 3 Oct 2017 | Service list · 3 Oct 2017 |
| DebtorEdge Residential Inc. | Bennett Jones LLP | 3 Oct 2017 | Service list · 3 Oct 2017 |
| DebtorUrbancorp Cumberland 2 GP Inc. | WeirFoulds LLP | 3 Oct 2017 | Service list · 3 Oct 2017 |
| CreditorAtrium Mortgage Investment Corporation | Teplitsky, Colson LLP | 3 Oct 2017 | Service list · 3 Oct 2017 |
| CreditorAviva Insurance Company of Canada | Rosensteinlaw P.c. | 24 Aug 2016 | Service list · 3 Oct 2017 |
| CreditorBMO | Chaitons LLP | 3 Oct 2017 | Service list · 3 Oct 2017 |
| CreditorCase Realty | Cassels Brock & Blackwell LLP | 24 Aug 2016 | Service list · 3 Oct 2017 |
| CreditorCIBC and CIBC Mortgage Inc | Torys LLP | 3 Oct 2017 | Service list · 3 Oct 2017 |
| CreditorDepartment of Justice | Robins Appleby LLP | 3 Oct 2017 | Service list · 3 Oct 2017 |
| CreditorDowning Street Financial Inc | Dickinson Wright LLP | 24 Aug 2016 | Service list · 3 Oct 2017 |
| CreditorFirst Capital Realty | Torys LLP | 3 Oct 2017 | Service list · 3 Oct 2017 |
| CreditorFirst Captial (King Liberty - Retail) Corporation, King Liberty North Corporation | Torys LLP | 24 Aug 2016 | Service list · 3 Oct 2017 |
| CreditorFuller Landau Group Inc | Goldman Sloan Nash & Haber LLP | 24 Aug 2016 | Order · 24 Aug 2016 |
| CreditorFurkin Construction Inc | Delzotto Zorzi, LLP | 24 Aug 2016 | Service list · 3 Oct 2017 |
| CreditorHomeLife Landmark Realty Inc | Fasken Martineau DuMoulin LLP | 28 Oct 2016 | Service list · 3 Oct 2017 |
| CreditorLaurentian Bank of Canada | Blake, Cassels & Graydon LLP | 24 Aug 2016 | Service list · 3 Oct 2017 |
| CreditorMDF Mechanical Limited | Torkin Manes LLP | 24 Aug 2016 | Service list · 3 Oct 2017 |
| CreditorMDF Mechanical Ltd | Garfinkle, Biderman LLP | 3 Oct 2017 | Service list · 3 Oct 2017 |
| CreditorMid-Northern | Miller Thomson LLP | 3 Oct 2017 | Service list · 3 Oct 2017 |
| CreditorMinistry of Finance | Torys LLP | 3 Oct 2017 | Service list · 3 Oct 2017 |
| CreditorParamount Structures Ltd | Drudi Alexiou Kuchar LLP | 24 Aug 2016 | Service list · 3 Oct 2017 |
| CreditorRBC and BNS | McMillan LLP | 24 Aug 2016 | Service list · 3 Oct 2017 |
| CreditorTarion Warranty Corporation | Torys LLP | 3 Oct 2017 | Service list · 3 Oct 2017 |
| CreditorTerra Firma Capital Corporation | Robins Appleby LLP | 3 Oct 2017 | Service list · 3 Oct 2017 |
| CreditorTerraplan Landscape Architects Ltd | Goldman Sloan Nash & Haber LLP | 26 Nov 2019 | Application · 26 Nov 2019 |
| CreditorToronto Media Arts Cluster | Goodmans LLP | 24 Aug 2016 | Service list · 3 Oct 2017 |
| CreditorToronto Standard Condominium Corporation No | Dickinson Wright LLP | 15 Mar 2019 | Application · 15 Mar 2019 |
| Priority class | Creditor | Amount | Source |
|---|---|---|---|
| Unsecured | Urbancorp Toronto Management Inc. · in 3 casesRelated party (Urbancorp group entity) — debtor: Westside Gallery Lofts Inc. · as of 20 Sep 2018 | $1.91M | Preliminary List of Creditors |
| Unsecured | |||
| Unsecured | |||
| Unsecured | |||
| Unsecured | |||
| Unsecured | |||
| Unsecured | |||
| Unsecured | |||
| Unsecured | |||
| Unsecured |
53 more claims in 1 class The stack holds Unsecured claims.
Every creditor and every amount, drawn to scale.
Card required. Nothing charged for 5 days. Cancel anytime.
Already a subscriber? Sign in.
See all plans10 transactions · 4 closed · 3 approved · 2 proposed · 1 not completed — approving the agreement of purchase and sale ... regarding sale of the Edge SpaceOrder of Chief Justice G.B. Morawetz dated December 3 2021 · 3 Dec 2021
| Purchaser | Price | Status | Source |
|---|---|---|---|
| 2494651 Ontario Inc.the purchased assets as described in the Sale Agreements and in Schedule "A" hereto (the "Purchased Assets") · real property · agreement 21 Oct 2016 | Sealed | Approved16 Dec 2016 | Approval and Vesting Order - Retail Units |
| Edland Realty Corporationthe purchased assets as described in the Sale Agreement and in Schedule "A" hereto (the "Purchased Assets") · real property · agreement 27 Oct 2016 | Subscribers | Approved16 Dec 2016 | Approval and Vesting Order - Edge Residential |
| purchasers of five Westside parking spots, unnamedindividual vacant parking spots situated at the lands and premises municipally known as 150 and 170 Sudbury Street, Toronto, Ontario · real property | Subscribers | Closed | Order Amending Approval and Vesting Order |
| unnamed offeror for Unit 101, Triangle buildingunit 101 · real property | Subscribers | Proposed | Monitor's Nineteenth Report |
| purchasers of Westside parking spots, unnamedthe Westside Parking Spot(s) · real property | not stated | Proposed | Monitor's Nineteenth Report |
| unnamedthree condominium units | not stated | Closeddate not stated | Monitor's Nineteenth Report |
| purchaser of unit 216, unnamed; sale described in sealed Confidential Appendix Athe sale of unit 216 · real property | Subscribers | Approved27 Sep 2019 | Order of Justice Morawetz (Approval of Sale of… |
| purchaser of condominium unit 316unit 316 · real property | Subscribers | Not completeddate not stated | Monitor's Twenty Fifth Report |
| purchasers of Westside Curve parking spotsParking Spots at the Curve building · real property | Subscribers | Closeddate not stated | Monitor's Twenty Fifth Report |
| 2509489 Ontario Inc.sale of the Edge Space (as defined below), residential condominium unit 1210E and 7 parking spots · asset sale · agreement 19 Nov 2021 | Sealed | Closeddate not stated | Monitor's Twenty-Third Report |
Unsecured creditors: a distribution. City of Toronto paid in full · Affinity paid in full.FinalMotion Record of the Monitor (53rd Report) · 27 Mar 2026
| Class | Creditor | Claims | Recovery | Basis | Source |
|---|---|---|---|---|---|
| Deemed trust | admitted Trust Claims | — | conditional | Estimatedper the monitor | Twenty Eighth Report of the Monitor · 31 Jul 2020 |
| Secured | Lien Claimants and Trust Claimants (Edge) | — | Finalper the monitor | 39th Report of the Monitor - February 24 2022 · 24 Feb 2022 | |
| Secured | City of Toronto | — | paid in full | Finalper the monitor | 40th Report of the Monitor · 26 May 2022 |
| Unsecured | — | — | of proven claimsinterim | Finalper the monitor | Motion Record of the Monitor (53rd Report) · 27 Mar 2026 |
| class not placedAffinity | Affinity | — | paid in full | Finalper the monitor | Monitor's Twenty-Third Report · 21 Aug 2019 |
Each row is one filing's statement, copied as it reads and never computed. "Estimated" is the officer's forecast; "Under the plan" is the plan's or proposal's own term; "Final" is a declared or paid distribution; a row with no chip states no footing. A range is the two numbers stated; "of proven claims" is the document's own denominator.
4 blurred figures above
The claims and what each class or creditor recovers — each as the filing states it, with its source.
Card required. Nothing charged for 5 days. Cancel anytime.
Already a subscriber? Sign in.
See all plans12 engagements · 3 firms — latest: The Fuller Landau Group Inc., to 31 Jan 2023, in feesForty-Fourth Report of the Monitor · 27 Feb 2023
| Firm | Period | Hours | Fees | Rates | Source |
|---|---|---|---|---|---|
| (firm not named)Trusteefirm not named in the heading | 22 Apr – 30 Jun 2016 | — | — | not stated | Motion Record - Returnable August 24, 2016 - Part 3 · 24 Aug 2016 |
| Goldman Sloan Nash & Haber LLPCounsel to the monitor | 1 Nov 2021 – 31 Jan 2022Sought | 2 people | Motion Record - Thirty-Ninth Report of the Monitor · 24 Feb 2022 | ||
| The Fuller Landau Group Inc.Monitorperiod 10 of 10 | to 31 Jan 2023 | — | 2 people | Forty-Fourth Report of the Monitor · 27 Feb 2023 | |
| The Fuller Landau Group Inc.Monitorperiod 9 of 10 | to 30 Nov 2022 | — | 4 people | Forty-Fourth Report of the Monitor · 27 Feb 2023 | |
| The Fuller Landau Group Inc.Monitorperiod 8 of 10 | to 30 Apr 2022 | — | 3 people | Motion Record - 40th Report of the Monitor · 26 May 2022 | |
| The Fuller Landau Group Inc.Monitorperiod 8 of 10 | 14 Apr – 30 Apr 2022 | — | 3 people | Motion Record - 40th Report of the Monitor · 26 May 2022 | |
| The Fuller Landau Group Inc.Monitorperiod 6 of 10 | 1 Mar – 13 Apr 2022 | — | 4 people | Motion Record - 40th Report of the Monitor · 26 May 2022 | |
| The Fuller Landau Group Inc.Monitorperiod 5 of 10 | 1 Feb – 28 Feb 2022 | — | — | not stated | Motion Record - 40th Report of the Monitor · 26 May 2022 |
| The Fuller Landau Group Inc.Monitorperiod 4 of 10 | 1 Oct – 31 Oct 2016Sought | Second Report of the Monitor - Part 3 · 2 Dec 2016 | |||
| The Fuller Landau Group Inc.Proposal trusteeperiod 3 of 10 | 1 May – 31 Aug 2016 | — | not stated | Motion Record - Returnable October 28, 2016 - Part 2 · 28 Oct 2016 | |
| The Fuller Landau Group Inc.Proposal trusteeperiod 2 of 10 | 22 Apr – 30 Jun 2016 | — | — | not stated | Motion Record - Returnable August 24, 2016 - Part 3 · 24 Aug 2016 |
| The Fuller Landau Group Inc.Proposal trusteeperiod 2 of 10 | 16 May – 30 Jun 2016 | — | — | not stated | Motion Record - Returnable August 24, 2016 - Part 3 · 24 Aug 2016 |
55 blurred figures above
What each firm billed, and each person’s hours and rate — each as the filing states it, with its source.
Card required. Nothing charged for 5 days. Cancel anytime.
Already a subscriber? Sign in.
See all plansAs at ·
Cumulative receipts
$5.26M
As at 31 Jul 2020Twenty Eighth Report of the Monitor
Cumulative disbursements
As at
Cash on hand
As at
Professional fees
As at
3 more reported figures, and the total the debtor stated at filing
Each one as the filing states it, with its source.
Card required. Nothing charged for 5 days. Cancel anytime.
Already a subscriber? Sign in.
See all plans| Date | Document | File |
|---|---|---|
Stay Extension Order dated October 1, 2026
| PDF · Subscribers | |
Stay Extension Order dated April 1, 2026
| PDF · Subscribers | |
Motion Record of the Monitor (53rd Report)
| PDF · Subscribers | |
Order-MotionforStayExtension-09Sept25
| PDF · Subscribers | |
| Stay Extension Order dated March 28, 2025 | PDF · Subscribers | |
Order of Justice Morawetz dated September 23 2024
| PDF · Subscribers | |
Motion Record dated Sept 17, 2024
| PDF · Subscribers | |
| Court Order dated May 28, 2024 | PDF · Subscribers | |
| Extension Order | PDF · Subscribers | |
| Motion Record of the Monitor | PDF · Subscribers | |
| Endorsement | PDF · Subscribers | |
Order of Justice Morawetz
| PDF · Subscribers | |
Forty-Seventh Report of the Monitor
| PDF · Subscribers | |
Forty-Sixth Report of the Monitor
| PDF · Subscribers | |
| Motion Record and Forty-Fifth Report of the Monitor | PDF · Subscribers | |
Forty-Fourth Report of the Monitor
| PDF · Subscribers | |
Endorsement of Justice Morawetz
| PDF · Subscribers | |
Forty-Third Report of the Monitor
| PDF · Subscribers | |
Forty-Second Report of the Monitor
| PDF · Subscribers | |
| Motion Record of the Monitor | PDF · Subscribers | |
| Endorsement of Justice Morawetz | PDF · Subscribers | |
| Order of Justice Morawetz | PDF · Subscribers | |
40th Report of the Monitor
| PDF · Subscribers | |
| Factum of the Monitor | PDF · Subscribers | |
Motion Record - 40th Report of the Monitor
| PDF · Subscribers | |
39th Report of the Monitor - February 24 2022
| PDF · Subscribers | |
| Factum of the Monitor | PDF · Subscribers | |
Motion Record - Thirty-Ninth Report of the Monitor
| PDF · Subscribers | |
Order of Chief Justice G.B. Morawetz dated December 3 2021
| PDF · Subscribers | |
| Factum of the Monitor | PDF · Subscribers | |
| Motion Record - Monitor's Thirty Eight Report | PDF · Subscribers | |
Thirty Eight Report of the Monitor
| PDF · Subscribers | |
Order of Chief Justice G.B. Morawetz
| PDF · Subscribers | |
| Motion Record - Monitor's Thirty-Seventh Report | PDF · Subscribers | |
Thirty Seventh Report of the Monitor
| PDF · Subscribers | |
Motion Record - Monitor's Thirty Sixth Report
| PDF · Subscribers | |
Thirty Sixth Report of the Monitor
| PDF · Subscribers | |
Thirty Fifth Report of the Monitor
| PDF · Subscribers | |
| Motion Record - Monitor's Thirty Fourth Report | PDF · Subscribers | |
Thirty Fourth Report of the Monitor
| PDF · Subscribers | |
Thirty Third Report of the Monitor
| PDF · Subscribers | |
| Distribution Order dated November 17, 2020 | PDF · Subscribers | |
Motion Record - Monitor's Thirty Second Report
| PDF · Subscribers | |
Thirty Second Report of the Monitor
| PDF · Subscribers | |
Order of Chief Justice Morawetz
| PDF · Subscribers | |
| Motion Record - Monitor's Thirty First Report | PDF · Subscribers | |
Thirty First Report of the Monitor
| PDF · Subscribers | |
Endorsement of Chief Justice Morawetz - October 2 2020
| PDF · Subscribers | |
| Motion Record - Monitor's Thirtieth Report | PDF · Subscribers | |
| Motion Record - Monitor's Twenty-Ninth Report | PDF · Subscribers | |
| Motion Record of the Monitor | PDF · Subscribers | |
Twenty Eighth Report of the Monitor
| PDF · Subscribers | |
Endorsement of Chief Justice Morawetz
| PDF · Subscribers | |
Monitor's Twenty-Sixth Report
| PDF · Subscribers | |
| Motion Record - Monitor's Twenty-Sixth report February 20, 2020 | PDF · Subscribers | |
| Endorsement of Chief Justice Morawetz | PDF · Subscribers | |
Monitor's Twenty-Second Report Supplement - November 26 2019
| PDF · Subscribers | |
Motion Record - Monitor's Twenty-Second Report Supplement - November 26 2019
| PDF · Subscribers | |
Monitor's Twenty Fifth Report
| PDF · Subscribers | |
| Motion Record - Monitor's Twenty-Fifth Report - November 20 2019 | PDF · Subscribers | |
Endorsement of Justice Morawetz (Approval of Sale of Unit 216) - September 27 2019
| PDF · Subscribers | |
Order of Justice Morawetz (Approval of Sale of Unit 216) - September 27 2019
| PDF · Subscribers | |
Motion Record - Monitor's Twenty Fourth Report - September 23 2019
| PDF · Subscribers | |
Endorsement of Chief Justice Morawetz (Stay Extension and directions re. Epic) - August 27 2019
| PDF · Subscribers | |
Order of Chief Justice Morawetz (Stay Extension and directions re. Epic) - August 27 2019
| PDF · Subscribers | |
Monitor's Twenty-Third Report
| PDF · Subscribers | |
Motion Record - Monitor's Twenty Third Report
| PDF · Subscribers | |
Endorsement of Chief Justice Morawetz - August 13 2019
| PDF · Subscribers | |
Order of Chief Justice Morawetz - August 13 2019
| PDF · Subscribers | |
Endorsement of Chief Justice Morawetz (Stay Extension) - July 25 2019
| PDF · Subscribers | |
Order of Chief Justice Morawetz (Stay Extension) - July 25 2019
| PDF · Subscribers | |
Monitor's Twenty-Second Report
| PDF · Subscribers | |
| Motion Record - Monitor's Twenty-Second Report | PDF · Subscribers | |
Endorsement of Justice Morawetz (Stay Extension)
| PDF · Subscribers | |
Order of Justice Morawetz (Stay Extension) - May 22 2019
| PDF · Subscribers | |
Monitor's Twenty-First Report
| PDF · Subscribers | |
| Motion Record - Monitor's Twenty-First Report | PDF · Subscribers | |
| D&O Proof of Claim | PDF · Subscribers | |
| Proof of Claim | PDF · Subscribers | |
| Endorsement - Appointment of Claims Officer | PDF · Subscribers | |
Order - Appointment of Claims Officer
| PDF · Subscribers | |
Monitor's Twentieth Report
| PDF · Subscribers | |
Motion Record - Monitor's Twentieth Report
| PDF · Subscribers | |
| Notice to Claimants | PDF · Subscribers | |
Approval and Vesting Order
| PDF · Subscribers | |
| Claimants' Guide to D&O Proof of Claim | PDF · Subscribers | |
| Claimants' Guide to Proof of Claim | PDF · Subscribers | |
| Claims Procedure Order | PDF · Subscribers | |
| Claims Procedure Order | PDF · Subscribers | |
Order of Justice Morawetz (Stay Extension)
| PDF · Subscribers | |
Monitor's Nineteenth Report
| PDF · Subscribers | |
| Motion Record - Monitor's Nineteenth Report | PDF · Subscribers | |
Endorsement of Justice Myers
| PDF · Subscribers | |
Order of Justice Myers
| PDF · Subscribers | |
Stay Extension Order of Justice Myers
| PDF · Subscribers | |
Monitor's Eighteenth Report
| PDF · Subscribers | |
| Motion Record - Monitor's Eighteenth Report | PDF · Subscribers | |
| Book of Authorities of Guy Gissin and Tarion Warranty Corporation | PDF · Subscribers | |
| Factum of Guy Gissin and Tarion Warranty Corporation | PDF · Subscribers | |
| Book of Authorities of Toro, Speedy, and Dolvin | PDF · Subscribers | |
| Factum of Toro, Speedy, and Dolvin | PDF · Subscribers | |
| Letter Supplement to Monitor's Seventeenth Report | PDF · Subscribers | |
| Motion Record - Second Supplement to Monitor's Seventeenth Report | PDF · Subscribers | |
Second Supplement to Monitor's Seventeenth Report
| PDF · Subscribers | |
Notice to Creditors
| PDF · Subscribers | |
Motion Record - Supplement to Monitor's Seventeenth Report
| PDF · Subscribers | |
Supplement to Monitor's Seventeenth Report
| PDF · Subscribers | |
Motion Record - Monitor's Seventeenth Report
| PDF · Subscribers | |
Monitor's Seventeenth Report
| PDF · Subscribers | |
| Monitor's Sixteenth Report | PDF · Subscribers | |
| Motion Record and Sixteenth Report of the Monitor | PDF · Subscribers | |
| Motion Record | PDF · Subscribers | |
| Monitor's Fifteenth Report | PDF · Subscribers | |
Order of Justice Myers dated May 9 2018
| PDF · Subscribers | |
| Monitor's Fourteenth Report | PDF · Subscribers | |
| Monitor's Thirteenth Report | PDF · Subscribers | |
| Motion Record - Returnable April 30, 2018 | PDF · Subscribers | |
| Endorsement of J. McEwen | PDF · Subscribers | |
| Motion Record - Volume 1 | PDF · Subscribers | |
| Motion Record - Volume 2 | PDF · Subscribers | |
Order of J. McEwen
| PDF · Subscribers | |
| Monitor's Twelfth Report | PDF · Subscribers | |
Dismissal Order
| PDF · Subscribers | |
| Endorsement of J. Hainey | PDF · Subscribers | |
Execution and Delivery of Minutes of Settlement and Entering into Occupancy Licence
| PDF · Subscribers | |
| Monitor's Eleventh Report | PDF · Subscribers | |
Order of J. Myers
| PDF · Subscribers | |
| Monitor's Tenth Report | PDF · Subscribers | |
| Motion Record - Tenth Report of the Monitor | PDF · Subscribers | |
| Monitor's Ninth Report | PDF · Subscribers | |
| Responding Written Submissions of the Edge Companies and Alan Saskin | PDF · Subscribers | |
| Motion Record of the Foreign Representative - Returnable January 22, 2018 | PDF · Subscribers | |
| Endorsement | PDF · Subscribers | |
| Supplementary Report to the Sixth Report | PDF · Subscribers | |
| Responding Motion Record of Cooltech, October 31, 2017 - Volume 1 of 2 | PDF · Subscribers | |
| Responding Motion Record of Cooltech, October 31, 2017 - Volume 2 of 2 | PDF · Subscribers | |
Service List
| PDF · Subscribers | |
| Order | PDF · Subscribers | |
| Responding Motion Record of the Canada Revenue Agency dated September 26, 2017 | PDF · Subscribers | |
| Monitor's Eighth Report | PDF · Subscribers | |
Endorsement of Myers J.
| PDF · Subscribers | |
| Monitor's Seventh Report | PDF · Subscribers | |
Court Order
| PDF · Subscribers | |
| Monitor's Sixth Report | PDF · Subscribers | |
| Motion Record - Sixth Report | PDF · Subscribers | |
| Monitor's Fifth Report | PDF · Subscribers | |
| Monitor's Fourth Report | PDF · Subscribers | |
| Motion Record - Fifth Report | PDF · Subscribers | |
| Motion Record - Fourth Report | PDF · Subscribers | |
| Monitor's Third Report | PDF · Subscribers | |
| D&O Proof of Claim | PDF · Subscribers | |
| Proof of Claim | PDF · Subscribers | |
Order Amending Approval and Vesting Order
| PDF · Subscribers | |
Approval and Vesting Order - Edge Residential
| PDF · Subscribers | |
Approval and Vesting Order - Edge on Triangle Park
| PDF · Subscribers | |
Approval and Vesting Order - Retail Units
| PDF · Subscribers | |
| Claimant's Guide to D&O Proof of Claim | PDF · Subscribers | |
| Claimant's Guide to Proof of Claim | PDF · Subscribers | |
| Motion Record - Returnable December 16, 2016 - Part 2 | PDF · Subscribers | |
| Motion Record - Returnable December 16, 2016 - Part 3 | PDF · Subscribers | |
| Motion Record - Returnable December 16, 2016 - Part 4 | PDF · Subscribers | |
Motion Record - Returnable December 16, 2016 - Part 5
| PDF · Subscribers | |
| Notice to Claimants | PDF · Subscribers | |
Stay Extension Order
| PDF · Subscribers | |
| Motion Record - Returnable December 16, 2016 - Part 1 | PDF · Subscribers | |
| Second Report of the Monitor - Part 1 | PDF · Subscribers | |
| Second Report of the Monitor - Part 2 | PDF · Subscribers | |
Second Report of the Monitor - Part 3
| PDF · Subscribers | |
| Second Report of the Monitor - Part 4 | PDF · Subscribers | |
Motion Record - Returnable October 28, 2016 - Part 2
| PDF · Subscribers | |
Motion Record - Returnable October 28, 2016 - Part 3
| PDF · Subscribers | |
| Motion Record - Returnable October 28, 2016 - Part 1 | PDF · Subscribers | |
| Application Record - Returnable October 6, 2016 - Part 2 | PDF · Subscribers | |
| Application Record - Returnable October 6, 2016 - Part 4 | PDF · Subscribers | |
| Book of Authorities - Returnable October 6, 2016 - Part 2 | PDF · Subscribers | |
| Book of Authorities - Returnable October 6, 2016 - Part 3 | PDF · Subscribers | |
| Book of Authorities - Returnable October 6, 2016 - Part 4 | PDF · Subscribers | |
CCAA Initial Order - Dated October 6, 2016
| PDF · Subscribers | |
| Book of Authorities - Returnable October 6, 2016 - Part 1 | PDF · Subscribers | |
| Factum - Returnable October 6, 2016 | PDF · Subscribers | |
| Trustee's Fourth Report - Part 1 | PDF · Subscribers | |
Trustee's Fourth Report - Part 2
| PDF · Subscribers | |
| Trustee's Fourth Report - Part 3 | PDF · Subscribers | |
| Application Record - Returnable October 6, 2016 - Part 1 | PDF · Subscribers | |
| Application Record - Returnable October 6, 2016 - Part 3 | PDF · Subscribers | |
Endorsement of Justice Hainey
| PDF · Subscribers | |
| Motion Record - Returnable August 24, 2016 - Part 2 | PDF · Subscribers | |
Motion Record - Returnable August 24, 2016 - Part 3
| PDF · Subscribers | |
Motion Record - Returnable August 24, 2016 - Part 4
| PDF · Subscribers | |
Order of Justice Hainey
| PDF · Subscribers | |
| Addendum to Third Report | PDF · Subscribers | |
| Motion Record - Returnable August 24, 2016 - Part 1 | PDF · Subscribers | |
| Trustee's Third Report | PDF · Subscribers | |
Endorsement of Justice Penny
| PDF · Subscribers | |
Order of Justice Penny
| PDF · Subscribers | |
| Trustee's Second Report - Part 1 | PDF · Subscribers | |
| Trustee's Second Report - Part 2 | PDF · Subscribers | |
| Motion Record - Returnable July 11, 2016 - Part 1 | PDF · Subscribers | |
| Report of Trustee for 1st Extension | PDF · Subscribers | |
| Motion Record - Returnable July 11, 2016 - Part 2 | PDF · Subscribers | |
| Motion Record - Returnable June 15, 2016 - Part 1 | PDF · Subscribers | |
| Interim Report to Creditors | PDF · Subscribers | |
Endorsement of Justice Newbould
| PDF · Subscribers | |
Motion Record Returnable May 26, 2016 - Part 2
| PDF · Subscribers | |
Order of Justice Newbould
| PDF · Subscribers | |
Motion Record - Returnable June 15, 2016 - Part 2
| PDF · Subscribers | |
| Trustee's First Report | PDF · Subscribers | |
| Certificate for the Notice of Intention | PDF · Subscribers | |
| Certificate for the Notice of Intention | PDF · Subscribers | |
Motion Record Returnable May 26, 2016 - Part 1
| PDF · Subscribers | |
| Certificate of Filing of a Notice of Intention | PDF · Subscribers | |
Certificate of Filing of a Notice of Intention
| PDF · Subscribers | |
| Certificate of Filing of a Notice of Intention | PDF · Subscribers | |
Preliminary List of Creditors
| PDF · Subscribers | |
Filing titles and dates are public, and so is each filing's own page. The figures read from them are for subscribers.
CiteProceedings., “Edge on Triangle Park Inc. et al.” (CCAA), Ontario Superior Court of Justice. Retrieved 4 November 2026, https://proceedings.ca/case/edge-on-triangle-park-inc