Proceedings.

Analysis · Case update

Moonlight Sonata: the monitor lines up a builder, and a guarantor asks out

Six weeks after Justice Milman gave AlixPartners the powers of the board over a stalled 51-townhome first phase in Burnaby, the monitor has disclaimed the Symphony group's construction management contract, chosen Townline Construction to negotiate a restart and reported that the project's BC Housing builder licence expired on July 31, 2025. The stay now runs to October 9, and the petitioners want 663466 B.C. Ltd., the founder's holding company, out of the CCAA.

Proceedings. ·

Gurmel Singh Kainth built his first single-family house in 1978, grew the Symphony group through the 1980s and into the early 2000s, and saw his son, Gurdeep, take over its management in 2006; he calls the group "the embodiment of my life's work in the construction industry," per his Affidavit No. 1 of Gurmel Singh Kainth, July 28, 2026, paras. 3–6. The group's Moonlight Sonata community was planned as 130 three- and four-bedroom townhomes and garden flats on 2.87 acres at 3588 Wayburne Drive in Burnaby, with Symphony Homes Limited, a group company, as construction manager, according to the Affidavit #1 of Gurdeep Singh Kainth, June 4, 2026, paras. 6, 20, 22. On August 4, 2026, the court-appointed monitor disclaimed that construction management contract, a CCDC-5B dated March 1, 2022. On September 2 it signed a limited site stabilization agreement with another builder, Townline Construction Inc., which has begun preparing the first phase for remobilization, per the Third Report of the Monitor, Sept. 4, 2026, s. 3.1, paras. 5, 13–15.

The petitioners are Symphony Homes (Moonlight Sonata) Limited, which holds title to the lands as nominee; 1168386 B.C. Ltd., 1197030 B.C. Ltd. and 1197062 B.C. Ltd., the beneficial owners; 663466 B.C. Ltd., a corporate guarantor; and Symphony Homes (Wayburne) Ltd., added at the comeback hearing. Their CCAA proceeding in the Supreme Court of British Columbia began on June 17, 2026, with AlixPartners Restructuring, Inc. as monitor and KingSett Mortgage Corporation, the senior secured lender, as interim lender under a facility of up to $27,900,000 on which borrowing was capped at $500,000 by the initial order and at $1,000,000 by the amended and restated initial order, per the Third Report of the Monitor, Sept. 4, 2026, s. 1.0, paras. 1, 3. Since July 29 the monitor has exercised the powers of the petitioners' boards. On September 10, on the monitor's application, Justice Milman extended the stay of proceedings to 11:59 p.m. on October 9, per the Order Made After Application, Sept. 10, 2026, para. 2. The petitioners, meanwhile, are asking the court to release 663466 B.C. Ltd. from the proceeding altogether.

How the monitor came to hold the board's powers

The petitioners' account of the insolvency is a dispute with their lender. KingSett committed two facilities totalling $95,300,000 under a commitment letter of September 27, 2024, amended April 15, 2025; on December 18, 2025, the borrowers learned it would suspend further draws, and on May 4, 2026 it demanded $59,121,710.51 and delivered a notice of intention to enforce security under section 244 of the Bankruptcy and Insolvency Act, per the Affidavit #1 of Gurdeep Singh Kainth, June 4, 2026, paras. 31, 34, 37, 59. The petitioners say KingSett also withdrew the loan's entire interest reserve on or around August 31, 2025 — its own July 31 statement had shown $6,572,991.04 — and that by their calculation the balance owing is $52,500,000, per their Notice of Application, July 28, 2026, Part 2, paras. 32, 36–37.

KingSett moved first, petitioning on June 1 for a creditor-led CCAA with an enhanced-powers monitor. Its affiant, Daniel Pollack, deposed that the lender had lost confidence over payment defaults, cost overruns, builders liens and "what appear to be improper withdrawals and misuse of holdback trust funds for personal and non-project-related expenses," per the Second Report of the Monitor, July 21, 2026, App. "A" (Affidavit #1 of Daniel Pollack), para. 4. The debtor-led proceeding that followed gave the monitor control of the bank accounts and required its approval for any disbursement above $10,000 in a single transaction, or $25,000 in the aggregate, per the same Second Report, s. 1.0, para. 2(c); s. 3.3, paras. 1–3.

Five weeks in, the monitor's Second Report set out what it had found. The debtors had given it a statement for the Wayburne account they said held the Builders Lien Act holdback, showing $1,228,086.21 on June 30, 2026; the statement AlixPartners obtained from TD showed an overdraft on that date and a balance that never exceeded about $20,000. The funds later wired to the monitor as holdback came through the account of Symphony Syndicate Corporation, a non-petitioner; the day after the monitor pressed for an explanation, its counsel was told that McEwan Partners had withdrawn as the debtors' counsel. The sale agreements required $4,170,155 in purchaser deposits; Dominion Law Group held $2,795,895 in trust, an apparent shortfall of $1,374,260. Two sale agreements KingSett had received in October 2025 did not appear in the debtors' ledgers. And in the TD statements for 663466 B.C. Ltd., the monitor found transfers above the approval threshold made without its knowledge, among them $150,000 on June 29, 2026, per the Second Report, ss. 4.1–4.3.

The petitioners answered on July 28. The inaccurate bank statement, they said, came from a person to whom day-to-day banking had been delegated while Gurdeep Kainth was away, acting without his knowledge and since removed; the holdback was "never deficient"; the 663466 account serves Gurmel Kainth's personal and business expenses, and he had not known the threshold applied to it. They asked the court to replace AlixPartners with Doane Grant Thornton LLP or, in the alternatives, to delete the monitor's banking and approval powers or move them to Doane Grant Thornton, to exempt 663466 from the approval threshold and to raise that threshold to $150,000, per the Notice of Application, July 28, 2026, Part 1, para. 1(f)–(i); Part 2, paras. 56–61. The monitor replied that nothing in those materials caused it to reconsider, and that "many of the explanations offered by the Petitioners reinforce the concerns previously identified by the Monitor," per the Supplement to the Second Report of the Monitor, July 29, 2026, s. 1.0, para. 4.

On July 29 Justice Milman granted KingSett's application; no order disposing of the petitioners' competing application appears on the docket. The monitor may now exercise "any powers the Monitor deems appropriate which may be properly exercised by the board of directors or any officers of the Petitioners," exclusively and "to the exclusion of all other Persons, including the Petitioners' directors," and may pay up to $500,000 of pre-filing debts to suppliers critical to construction, per the Enhanced Powers and Stay Extension Order, July 29, 2026, paras. 3, 5. Two days later the monitor wrote to the pre-sale purchasers: "You should not seek or act on instructions from the principals, directors, officers, management or other representatives of Symphony in respect of the Project," per its Notice to Moonlight Sonata Purchasers, July 31, 2026, p. 1. On August 18 the petitioners filed a notice of appeal seeking leave to appeal the order; they have not sought a stay of it, per the Third Report, s. 1.0, para. 3(d).

Six weeks at the controls

The Third Report describes a site that has been substantially inactive since the fourth quarter of 2025. Only Phase 1A, 51 for-sale townhomes that management had put at about 78% complete, is under development; 26 are sold, 25 are not, and the sale agreements let purchasers rescind if their units are not finished by May 2027, which the monitor calls "a matter of material importance to the Debtors' stakeholders." KingSett was owed approximately $59.6 million on May 31, 2026, before interim advances; 25 lien claimants had registered approximately $7.5 million against the lands, and the books showed approximately $2.3 million in unsecured debt. The monitor is still reviewing the deposit shortfall, the two missing sales and the related-party transactions, per the Third Report, s. 2.0, paras. 4–8.

Within a week of the order it had begun replacing the construction manager. It also disclaimed a September 25, 2023 lease of premises at 5648 Imperial Street, Burnaby, held by Symphony Homes (Wayburne) Ltd.; Symphony Homes Limited did not apply within the 15-day window to contest the disclaimer of its contract. On August 4 the monitor issued a request for proposals to four parties with development and construction experience, one of them, the report says, "the Petitioner," with proposals due August 12. After consulting KingSett it chose Townline as the party with which to negotiate construction and development management agreements, which will come back to the court for approval, per the Third Report, s. 3.1, paras. 5–6, 8–11.

The monitor's review has also turned up historical permitting and licensing matters that must be dealt with before construction can fully resume, including outstanding items on the building permits and inspections. The residential builder licence issued by BC Housing and used for the project expired on July 31, 2025 and "does not appear to have been renewed by the Petitioners," per the Third Report, s. 3.2, paras. 1–2. The monitor prepared the new cash flow forecast itself, so it carries no management representations. For September 7 to October 11 it projects $573,000 of disbursements, including $250,000 of professional fees and $210,000 of project soft costs, funded by $600,000 of interim draws and closing at $31,000. About $210,000 had been advanced as of the report, mostly for property taxes, insurance and security, leaving roughly $790,000 of approved availability. The forecast leaves out "the material costs associated with the full remobilization and recommencement of construction," per the Third Report, s. 4.0, paras. 2–6.

The holding company and the invoices

On August 27 the petitioners, joined by Symphony Homes Limited, applied for two orders: removing 663466 B.C. Ltd. as a petitioner, and directing the monitor to pay, within five days, Symphony Homes Limited's construction management invoices and a set of services invoices, per the Notice of Application, Aug. 27, 2026, Part 1, para. 1.

Gurmel Kainth, the sole director and shareholder of 663466, affirmed the evidence for removing it. Under the April 2025 amendment to the KingSett commitment, 663466 gave a guarantee and a second mortgage on 414–416 East Columbia Street in New Westminster, collateral he says he agreed to provide only because it was temporary and would be released once the conditions for the loan's second facility were met. Early in 2026, he deposes, "the Lender unilaterally decided that it would no longer fund Facility 2," so those conditions could never be satisfied, per the Affidavit #2 of Gurmel Singh Kainth, Aug. 26, 2026, paras. 7, 13, 18–22. An amended and restated commitment letter presented on January 8, 2026, which the Kainths understood would discharge that collateral, was never fully executed, according to the Affidavit #6 of Gurdeep Singh Kainth, Aug. 26, 2026, paras. 12, 22–23. Since July 29 Gurmel Kainth has had no access to the company's account, which he says he has held for more than 23 years and uses for mortgage payments, utilities, property taxes, water and sewer charges and about $2,500 a month in interest. "I risk defaulting on my mortgage payments," he deposes, per the Affidavit #2 of Gurmel Singh Kainth, Aug. 26, 2026, paras. 14–16.

The application argues that 663466 holds no project contracts and serves no restructuring purpose, that it "should never have been included as a Petitioner in these proceedings in the first place," and that KingSett's security stands whether or not it remains. It adds that the Toronto-Dominion Bank, which holds the first mortgage on the company's land, was never put on notice that the administration charge and interim financing would rank ahead of it, per the Notice of Application, Aug. 27, 2026, Part 2, paras. 17–22; Part 3, paras. 36–40.

The invoices cover June 17 to July 29, the weeks before the monitor took control. The petitioners say Symphony Homes Limited prepared budgets, schedules, cash flow forecasts and cost-to-complete analyses at the monitor's instruction, and paid some third-party site costs in advance. The preservation invoices they list — fence, site labour, equipment and generator rentals, alarm monitoring and $5,250 of accounting — total $23,343.89; because that is under the $25,000 aggregate threshold, with no item above $10,000, they submit no approval was needed, and in any event the amounts sit well within the $67,000 the monitor's first cash flow allowed for site security and maintenance. "The fact that the director of both Symphony and the project-related Petitioners is the same does not allow the Monitor to pick and choose when certain services are provided by the project-related Petitioners versus Symphony to avoid paying construction management costs that are due and owing in the ordinary course of business," the notice says, per the Notice of Application, Aug. 27, 2026, Part 2, paras. 27–31; Part 3, paras. 47–50, 54.

The monitor has told the petitioners' counsel that removing 663466 and paying "the purported post-filing construction management invoices is not appropriate," and it will oppose. It has offered to review the services invoices and authorize whatever is properly payable and contemplated by the filed cash flows. It also reports that the petitioners have acknowledged receiving an $86,185.66 GST/HST refund that, in its view, belongs to the estate, and that the money has not arrived despite counsel's advice that it would be returned, per the Third Report, s. 3.3, paras. 1–3. The petitioners had said in July that the refund arose from GST paid with money from Symphony, the Kainths and other sources outside KingSett's draws, and offered to hold it in their counsel's trust account, per the Notice of Application, July 28, 2026, Part 2, paras. 85–88.

Four weeks more

The monitor's stay application, estimated at 15 minutes and granted on September 10, rested on s. 11.02 of the CCAA and on the submission that "The Petitioners, through the Monitor and the Enhanced Powers, have been working in good faith and with due diligence to complete the Project for the benefit of all stakeholders," per its Notice of Application, Sept. 4, 2026, Part 3, paras. 13–15. KingSett supported the extension, and the monitor knew of no one opposed, per the Third Report, s. 5.0, para. 4.

The August 27 application was filed returnable September 9, but the monitor understands the petitioners intend to have it heard on October 1. Before the stay expires on October 9, the monitor intends to return to court on the restart: the appointment of a construction and development manager, interim financing requirements and related relief. Its disclaimer of the Imperial Street lease takes effect on September 20 unless the landlord, Koreana Enterprises Ltd., objected by September 5, per the Third Report, s. 3.1, para. 6; s. 3.3, para. 1; s. 5.0, para. 3.

Every fact above names the filing it was read from.

Case pages are free to browse. The subscription unlocks the filings themselves, and our full analysis.

Subscribe

Analysis is editorial; every factual claim cites the record. The record itself never editorializes.

Facts and summaries are extracted automatically from the court filings linked on each page; the filings remain the authoritative record. Suggested corrections are reviewed against the source filings.