Green World Construction Inc.
Follow- Proceeding
- Receivership (court-appointed)Subsection 243(1) of the Bankruptcy and Insolvency Act, R.S.C. 1985, c. B-3, as amended, and section 101 of the Courts of Justice Act, R.S.O. 1990, c. C.43, as amended
- Court
- Ontario Superior Court of Justice · Commercial List
- File
- CV-25-00740691-00CL
Green World Construction Inc. has been in court-appointed receivership since May 20, 2025, when the Ontario Superior Court of Justice (Commercial List) appointed KSV Restructuring Inc. as receiver and manager on the application of 2106580 Ontario Inc. and Osmington (Wood Street) Inc., under subsection 243(1) of the Bankruptcy and Insolvency Act and section 101 of the Courts of Justice Act. A sale process approved September 12, 2025 produced a teaser to 179 potential purchasers and six signed NDAs, but no letters of intent by the October 13 deadline, leaving the stalking horse agreement with Aggregated Investments Inc. at a purchase price of $34,220,000 as the successful bid. The Court approved that transaction on October 21, 2025. In its Third Report dated November 26, 2025, the Receiver reported on closing and on its calculation of the distribution to Osmington. Court file CV-25-00740691-00CL.
Third Report covered closing the transaction, review of Osmington's payout statement and the statement of adjustments, calculation of the distribution to Osmington, property maintenance and security arrangements, and approximately $1,250,000 of cash on hand. Reported fees: Receiver $44,443.75 for October, Paliare Roland $8,561, Osler $34,701.00.
Source: Third Report of the Receiver dated November 26, 2025
Approved the transaction with Aggregated Investments Inc., with the purchased assets to vest on delivery of the Receiver's Certificate confirming payment and completion.
Second Report reported the sale process launched September 16, 2025, a teaser to 179 parties, six NDAs and no letters of intent, and recommended approval of the $34,220,000 stalking horse bid and a distribution order. Receiver's fees of $163,635.75 to September 30 and Paliare Roland's fees of $32,892.50 to October 9 were reported.
Source: Second Report of the Receiver dated October 16, 2025
Motion Record of the Receiver re Sale Approval dated October 16, 2025 — Application / notice of application
Approved the Receiver's sale process for the Property, with the stalking horse agreement of purchase and sale with Aggregated Investments Inc. as the baseline bid.
Source: Green World Sale Process
Authorized a break fee of $855,500 payable to the stalking horse bidder under the approved sale process.
Fixed the sale process timetable, with a Phase 1 letter of intent deadline of October 13, 2025 and a bid deadline of October 28, 2025.
Source: Sale Process and Stalking Horse Order dated September 12, 2025
First Report set out initial administration: securing and monitoring the Property, opening the estate account, filing quarterly HST returns, notifying creditors, establishing the case website, and rezoning and due diligence correspondence.
Source: First Report of the Receiver dated September 5, 2025
Appointed KSV Restructuring Inc. receiver and manager on the applicants' motion, granted a stay, and created a first-ranking Receiver's Charge plus a $1,000,000 Receiver's Borrowings Charge.
Undated filings1 — no date appears on the document · show
Debtor
Green World Construction Inc.
Applicant
2106580 Ontario Inc.,Osmington (Wood Street) Inc.
Receiver
KSV
Bench
| Judge | Court | On this docket | Cases on record |
|---|---|---|---|
| Justice Cavanagh | Ontario Superior Court of Justice | 4 orders, Apr 2025 – Oct 2025 | 288 cases on record |
| Justice Steele | Ontario Superior Court of Justice | 3 orders, Sep 2025 | 220 cases on record |
| Justice Conway | Ontario Superior Court of Justice | 2 orders, Dec 2025 | 285 cases on record |
Counsel of record
| Party | Counsel | First seen | Source |
|---|---|---|---|
| ReceiverKSV | Rothstein LLP · Paliare Roland LLP | 8 Sep 2025 | Order · 21 Oct 2025 |
| Applicant2106580 Ontario Inc.,Osmington (Wood Street) Inc. | Osler, Hoskin & Harcourt LLP | 10 Apr 2025 | Affidavit · 10 Apr 2025 |
| CreditorOrder | Rothstein LLP | 15 Sep 2025 | Sale Process Letter · 15 Sep 2025 |
| # | Priority class | Creditor | Amount | Source |
|---|---|---|---|---|
| Court-ordered charges | ||||
| 1 | Court-ordered charges | Receiver's Borrowings Charge — in priority to all security interests, trusts (including, without limitation, deemed trusts), liens, charges and encumbrances, statutory or otherwise, in favour of any Person but subordinate in priority to the Receiver's | $1M | Receivership Order dated May 20, 2025 |
| 1 | Court-ordered charges | Receiver's Charge — shall form a first charge on the Property in priority to all security interests, trusts (including, without limitation, deemed trusts), liens, charges and encumbrances, statutory or otherwise, in favour of any Person, bu | — | Receivership Order dated May 20, 2025 |
| Pre-filing debt | ||||
| 4 | Secured | Osmington (Wood Street) Inc. and 2106580 Ontario Inc. (collectively, "Osmington")Charge on title to the Property (175-199 Essa Road and 50 Wood Street, Barrie) registered April 14, 2022 in the registered amount of $48.03 million (registration ceiling, not the outstanding balance) — Prose states owed 'approximately $31.39 million as of April 4, 2025'; exact figure of $31,390,662.00 appears in the Receiver's preliminary list of creditors as at May 20, 2025 (Appendix A). Interest and costs continue to accrue. — debtor: Green World Construction Inc. · as of 4 Apr 2025 | $31.4M | Notice & Statement of the Receiver dated May 30, 2025 |
| 4 | Secured | MarshallZehr Group Inc. · in 19 casesCharge on title to the Property registered April 14, 2022 in the registered amount of $13.30 million (registration ceiling, not the outstanding balance) — Loan is subordinated and postponed in favour of Osmington's loan pursuant to a subordination agreement dated April 14, 2022 among Osmington, MarshallZehr, the Debtor and Digram Developments, as guarantor (guarantee - related party not itself a creditor here). Interest and costs continue to accrue. Exact balance of $12,712,188.21 taken from Appendix A preliminary list of creditors as at May 20, 2025. — debtor: Green World Construction Inc. · as of 20 May 2025 | $12.7M | Notice & Statement of the Receiver dated May 30, 2025 |
| 8 | Unsecured | Mohsin MasoodIndividual creditor, not a guarantor. — debtor: Green World Construction Inc. · as of 20 May 2025 | $26.8M | Notice & Statement of the Receiver dated May 30, 2025 |
| 8 | Unsecured | Tor Construction Limiteddebtor: Green World Construction Inc. · as of 20 May 2025 | $4.75M | Notice & Statement of the Receiver dated May 30, 2025 |
| 8 | Unsecured | City of Barrie · in 3 casesMunicipality; document does not designate this claim as preferred. — debtor: Green World Construction Inc. · as of 20 May 2025 | $787K | Notice & Statement of the Receiver dated May 30, 2025 |
| 8 | Unsecured | Soil Engineers Ltd. · in 3 casesdebtor: Green World Construction Inc. · as of 20 May 2025 | $174K | Notice & Statement of the Receiver dated May 30, 2025 |
| 8 | Unsecured | Loopstra Nixon · in 2 casesdebtor: Green World Construction Inc. · as of 20 May 2025 | $84.9K | Notice & Statement of the Receiver dated May 30, 2025 |
| 8 | Unsecured | Innovative Planning Solutions · in 2 casesdebtor: Green World Construction Inc. · as of 20 May 2025 | $38.4K | Notice & Statement of the Receiver dated May 30, 2025 |
| 8 | Unsecured | Wellington Dupont Canada Inc.debtor: Green World Construction Inc. · as of 20 May 2025 | $21.5K | Notice & Statement of the Receiver dated May 30, 2025 |
| 8 | Unsecured | Caliber Communicationsdebtor: Green World Construction Inc. · as of 20 May 2025 | $19.8K | Notice & Statement of the Receiver dated May 30, 2025 |
| 8 | Unsecured | SGL Planning & Design Inc.debtor: Green World Construction Inc. · as of 20 May 2025 | $7.68K | Notice & Statement of the Receiver dated May 30, 2025 |
| 8 | Unsecured | ISM Architectsdebtor: Green World Construction Inc. · as of 20 May 2025 | $6.38K | Notice & Statement of the Receiver dated May 30, 2025 |
| 8 | Unsecured | Azimuth Environmental Consulting Inc. · in 2 casesdebtor: Green World Construction Inc. · as of 20 May 2025 | $3.07K | Notice & Statement of the Receiver dated May 30, 2025 |
| 8 | Unsecured | Kuntz Forestry Consulting Inc. · in 2 casesdebtor: Green World Construction Inc. · as of 20 May 2025 | $2.44K | Notice & Statement of the Receiver dated May 30, 2025 |
| 8 | Unsecured | BEZIERCG LIMITEDForeign creditor (Hong Kong). — debtor: Green World Construction Inc. · as of 20 May 2025 | $1.7K | Notice & Statement of the Receiver dated May 30, 2025 |
| 8 | Unsecured | Counterpoint Engineeringdebtor: Green World Construction Inc. · as of 20 May 2025 | $1.13K | Notice & Statement of the Receiver dated May 30, 2025 |
| 8 | Unsecured | BA Consulting Groupdebtor: Green World Construction Inc. · as of 20 May 2025 | $593 | Notice & Statement of the Receiver dated May 30, 2025 |
“not stated” means the record names the claim without a figure; “—” means not in the extracted record.
Sale approvedApproval and Vesting Order dated October 21, 2025 · 21 Oct 2025
| Purchaser | Price | Status | Source |
|---|---|---|---|
| Aggregated Investments Inc. | not stated | Approved21 Oct 2025 | Approval and Vesting Order dated October 21,… |
other stakeholders: no distribution.EstimatedMotion Record of the Receiver · 26 Nov 2025
| Class | Creditor | Claims | Recovery | Basis | Source |
|---|---|---|---|---|---|
| class not placed | other stakeholders | — | no distribution | Estimatedper the receiver | Motion Record of the Receiver · 26 Nov 2025 |
Each row is one filing's statement, copied as it reads and never computed. "Estimated" is the officer's forecast; "Under the plan" is the plan's or proposal's own term; "Final" is a declared or paid distribution; a row with no chip states no footing. A range is the two numbers stated; "of proven claims" is the document's own denominator.
6 engagements · 3 firms — latest: Osler, Hoskin & Harcourt LLP, 14 Oct – 5 Nov 2025, $34,701.00 in feesMotion Record of the Receiver · 26 Nov 2025
| Firm | Period | Hours | Fees | Rates | Source | ||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| KSV Restructuring Inc.Receiverperiod 1 of 2 | to 30 Jun 2025 | — | — | $661.15stated average | Second Report of the Receiver · 16 Oct 2025 | ||||||||||||||||||||||||||||||
| KSV Restructuring Inc.Receiverperiod 1 of 2 | October, 2025 | 66.9 | $44,443.75 | $600 – $8503 people | Motion Record of the Receiver · 26 Nov 2025 | ||||||||||||||||||||||||||||||
3 people — KSV Restructuring Inc., October, 2025
| |||||||||||||||||||||||||||||||||||
| Osler, Hoskin & Harcourt LLPCounsel to the receiverperiod 2 of 2 | 14 Oct – 5 Nov 2025 | 37.9 | $34,701.00ex. tax | $420 – $1,2004 people | Motion Record of the Receiver · 26 Nov 2025 | ||||||||||||||||||||||||||||||
4 people — Osler, Hoskin & Harcourt LLP, 14 Oct – 5 Nov 2025
| |||||||||||||||||||||||||||||||||||
| Osler, Hoskin & Harcourt LLPCounsel to the receiverperiod 1 of 2 | — | 34.8 | $33,963.00 | $420 – $1,6505 people | Motion Record of the Receiver · 26 Nov 2025 | ||||||||||||||||||||||||||||||
5 people — Osler, Hoskin & Harcourt LLP, —
| |||||||||||||||||||||||||||||||||||
| Paliare Roland Rosenberg Rothstein LLPCounsel to the receiverperiod 2 of 2 | to 9 Oct 2025 | — | — | $828.50stated average | Second Report of the Receiver · 16 Oct 2025 | ||||||||||||||||||||||||||||||
| Paliare Roland Rosenberg Rothstein LLPCounsel to the receiverperiod 1 of 2 | to 30 Jun 2025 | — | — | $828.50stated average | Motion Record of the Receiver re Sale Approval · 16 Oct 2025 | ||||||||||||||||||||||||||||||
Top rate $1,200 · 71st percentile of counsel rates, 2025 · of 80
As at 20 May 2025 · per Preliminary list of creditors (unaudited), based on books and records of Green World Construction Inc.; balances preliminary, subject to change and may differ from creditors' records · Green World Construction Inc. (the Debtor) — Total is the sum of Total Secured Creditors ($44,102,850.21) and Total Unsecured Creditors ($32,662,044.88) as stated in Appendix A. The Receiver states: 'The Receiver was not provided a copy of the financial statements from the Debtor and accordingly the book value of the assets is not available' (page 1), so total_assets is not stated.
Cash on hand
$1.25M
As at 26 Nov 2025Third Report of the Receiver dated November 26, 2025
Professional fees to date
KSV Restructuring Inc. (Receiver): $163,635.75; Paliare Roland Rosenberg Rothstein LLP: $32,892.50
As at 16 Oct 2025Second Report of the Receiver dated October 16, 2025
| Date | Document | File |
|---|---|---|
| Receiver's Discharge Certificate dated May 20, 2026 | ||
Discharge Order dated December 2, 2025
| ||
Endorsement of Justice Conway dated December 2, 2025
| ||
Aide Memoire of the Receiver dated December 1, 2025
| ||
Aide Memoire of the Receiver dated November 27, 2025
| ||
Motion Record of the Receiver dated November 26, 2025
| ||
Third Report of the Receiver dated November 26, 2025
| ||
Approval and Vesting Order dated October 21, 2025
| ||
Distribution Order dated October 21, 2025
| ||
Endorsement of Justice Cavanagh dated October 21, 2025
| ||
Motion Record of the Receiver re Sale Approval dated October 16, 2025
| ||
Second Report of the Receiver dated October 16, 2025
| ||
Sale Process Letter dated September 15, 2025
| ||
Endorsement of Justice Steele dated September 12, 2025
| ||
Green World Sale Process
| ||
Sale Process and Stalking Horse Order dated September 12, 2025
| ||
Factum of the Receiver dated September 8, 2025
| ||
First Report of the Receiver dated September 5, 2025
| ||
| Motion Record of the Receiver dated September 5, 2025 | ||
Notice & Statement of the Receiver dated May 30, 2025
| ||
Endorsement of Justice Cavanagh dated May 20, 2025
| ||
| Non Disclosure Agreement | ||
Receivership Order dated May 20, 2025
| ||
Supplemental Affidavit of Jason Levin dated May 15, 2025
| ||
Endorsement of Justice Cavanagh dated April 14, 2025
| ||
Factum of the Applicants dated April 10, 2025
| ||
Supplemental Affidavit of Jason Levin dated April 10, 2025
| ||
Application Record dated April 7, 2025
| ||
| Teaser | ||
Filing titles, dates, and extracted key facts are public.
CiteProceedings., “Green World Construction Inc.” (Receivership (court-appointed)), Ontario Superior Court of Justice · Commercial List. Retrieved 20 September 2026, https://proceedings.ca/case/green-world-construction-inc