Proceedings.

Analysis · Filing brief

Clarkson Road: the lien claimant who paid out the DIP

A townhouse project in Mississauga spent two years in CCAA, won approval for an insider recapitalization that never found its financing, and then sat for six months with its stay lapsed. On September 8, 2026, Justice Cavanagh appointed PwC as receiver on the application of Kenaidan Contracting — by consent, in an order that takes effect only once Kenaidan funds a $10,549,924 payout of the charges held by the lender that had asked for a different receiver.

Proceedings. · · 7 min read

The land at 1111 Clarkson Road sits south of the QEW, close to the Clarkson GO station in Mississauga, and the plan for it was five townhouse buildings with 176 units and 28,000 square feet of commercial space, per the Pre-Filing Report of the Proposed Monitor, May 3, 2024, pp. 9–10. When the developers filed under the CCAA in May 2024, construction had been stopped since the previous August over a dispute with the construction manager, and "approximately 60% of the parking structure is at grade level, with the remainder below-grade and not fully covered or sealed." The site needed fencing, protection for the below-grade structure, dewatering and daily safety and structural monitoring, per the Endorsement of Cavanagh J. re Initial Order, May 3, 2024.

The construction manager was Kenaidan Contracting Ltd. On September 8, 2026, in a new application under its own court file, Justice Cavanagh appointed PricewaterhouseCoopers Inc. — the CCAA monitor since 2024 — as receiver of the five debtor entities on Kenaidan's application. Kenaidan holds "two perfected construction lien claims totalling over $25 million." The endorsement gives the history in three sentences: "Over approximately two years, the CCAA Proceedings failed to produce a viable transaction to maximize value for stakeholders. In late 2025, the DIP Lender ceased funding, leaving the CCAA Proceedings without resources to continue. The stay of proceedings lapsed on February 28, 2026 and has not been renewed," per the Endorsement of Cavanagh J. re Receivership, Sept. 8, 2026, paras. 1–2.

The debt, and who was on which side of it

The developers are part of what the proposed monitor called the South Shore Group, a Greater Toronto Area developer. They bought the land partly with a $20 million vendor take-back mortgage, which passed to CS Capital Limited in December 2023, per the Pre-Filing Report of the Proposed Monitor, May 3, 2024, p. 10. By filing, the mortgage was in default, CS Capital had begun enforcing, and construction liens of approximately $27 million were registered against the property. CS Capital supported the filing as a route to a quick sale process with a stalking horse.

The proposed monitor described the fight with Kenaidan as it understood it. Construction had been funded through a deferred payment arrangement under which payments to Kenaidan would wait for third-party financing; the developers and Kenaidan were in dispute over that arrangement and over the developers' allegations that Kenaidan's work was over budget and its claims unsupported or not payable; and Michael Moldenhauer had talked to Kenaidan about what was owed without reaching a settlement, per the Pre-Filing Report of the Proposed Monitor, May 3, 2024, pp. 10–11. Kenaidan's lien claim has never been adjudicated; the claims procedure approved in September 2025 was not completed.

A six-month option

The sale process ran for eight weeks through CBRE and drew no qualified bid except the stalking horse, an investment agreement with 1000861289 Ontario Inc. In August 2025 the developers brought back an amended and restated version: the investor would assume or pay every claim ranking ahead of the construction liens and pay $22 million in cash, a transaction the monitor valued at approximately $35.2 million plus assumed liabilities as of a February 23, 2026 closing, per the Endorsement of Cavanagh J., Sept. 11, 2025, paras. 14, 31, 39, 42. The investor needed about six months to raise the money.

The monitor put the closing risks on the record. There was no financing condition, but without financing there would be no closing. And "the Investor and the DIP lender are under common control," with the agreement letting the investor decide whether the DIP debt was assumed or paid out. Kenaidan, the largest creditor, supported the deal; so did CS Capital; the DIP lender said it would not fund another sale process. Delgant (T.O.) Limited, a lien claimant, opposed it, arguing that the deal was "in substance a six-month option for the principal of the Applicant Entities, the DIP Lender and the Investor to attempt to re-acquire the property if their principal is able to secure financing," and noting that the purchaser was "controlled by Michael Moldenhauer who is the principal of the Applicants, the Investor, and the DIP Lender," per the Endorsement of Cavanagh J., Sept. 11, 2025, paras. 12, 15–16, 22–25.

Justice Cavanagh approved it on September 11, 2025. He accepted that the agreement had conditions "which introduce considerable uncertainty concerning whether the transaction contemplated thereby will close," but found the market had been tested, that the broker's advice was that it had deteriorated since, and that there was no evidence financing existed for a new process. A reverse vesting order was needed to keep the building permits and the agreements with the City of Mississauga and the Region of Peel. The transaction did not yield "any recovery for unsecured creditors or equity holders," per the Endorsement of Cavanagh J., Sept. 11, 2025, paras. 27–30, 36–40. The stay was extended to February 28, 2026, and the general and construction DIP facility was raised from $5.875 million to $7.2 million to carry the site in care and maintenance, with no construction, until closing, per the Endorsement of Cavanagh J., Sept. 11, 2025, paras. 17, 53–59.

February

The additional $1.325 million never arrived. By February 9, 2026, the monitor reported that the developers and the DIP lender had failed to find replacement liquidity and that "no further DIP financing is available to fund the forecast payments contemplated in the Eighth Cash Flow Forecast." Accrued professional fees exceeded the administration charge and the subordinated administration charge combined. The developers had not given the monitor current financial information or bank statements despite its requests. The investor had not secured its exit financing, the transaction would not close, and the investor was not asking for more time. The monitor did not expect the developers to seek another stay extension and anticipated that one or more stakeholders "will seek further relief from this Court prior to the end of February," per the Eleventh Report of the Monitor, Feb. 9, 2026, paras. 9–19.

Keep reading with a 5-day free trial

About 3 more minutes of this analysis, and 2 more sections. Every fact in it cites the filing it was read from.

Start 5-day trial

Card required. Nothing charged for 5 days. Cancel anytime.

Already a subscriber? Sign in.

See all plans⁠

Analysis is editorial; every factual claim cites the record. The record itself never editorializes.

Facts and summaries are extracted automatically from the court filings linked on each page; the filings remain the authoritative record. Suggested corrections are reviewed against the source filings.