Ontario · Receivership (court-appointed)
Fourth Report of Interim Receiver
Court officer report · 20 August 2021
A plain-language read of this filing opens with a subscription.
What we verified from this filing3 verified
- operational summaryPhase 1 construction of the mixed-use retail/gas station development is continuing but has been delayed by prior contractor errors (misplaced curbs, defective asphalt, unflushed sanitary lines); the Interim Receiver expects Phase 1 to be completed within about four weeks but estimates an additional $250,000 is needed beyond original borrowings, excluding remaining gas station work.
- report date20 August 2021
- report noFourth Report